Filter by category
Filter by Date
Direction - SA region 05/07/2024
Direction - SA region 05/07/2024
Refer to Market Notice 117292
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1700 hrs 05/07/2024
Type of resource: generating unit
Required actions: remain synchronised and follow dispatch targets at 0100 hrs 06/07/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1600 hrs 06/07/2024
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Update - Foreseeable AEMO intervention in SA region
Update - Foreseeable AEMO intervention in SA region
Refer AEMO Electricity Market Notice 117291
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0001 hrs 06/07/2024.
The foreseeable circumstance requiring the need for intervention is Voltage.
AEMO estimates that, in the absence of sufficient market response by 1700 hrs 05/07/2024, AEMO may need to intervene by issuing a direction.
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0001 hrs 06/07/2024.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
Cancellation - Possible intervention to manage power system security in SA region 05/07/2024
Cancellation - Possible intervention to manage power system security in SA region 05/07/2024
Refer Market Notice 117281
AEMO no longer foresees a possible requirement for intervention to manage power system security in SA region. The advice of possible intervention is cancelled from 0845 hrs 04/07/2024.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Wednesday, 3 July 2024
NON-CONFORMANCE QLD1 Region Wednesday, 3 July 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: CALL_B_1
Duration: 03/07/2024 21:55 to 03/07/2024 22:00
Amount: -97 MW
Constraint: NC-Q_CALL_B_1
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 03/07/2024
Cancellation of Actual (LOR1) condition in the NSW region - 03/07/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.117284 is cancelled at 2010 hrs 03/07/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 03/07/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 03/07/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs
The capacity reserve requirement is 1400 MW
The minimum capacity reserve available is 766 MW
Manager NEM Real Time Operations
Update - Possible intervention to manage power system security in SA region
Update - Possible intervention to manage power system security in SA region
Refer AEMO Electricity Market Notice 117278
The synchronous generating units currently expected to be synchronised in SA from 0000 hrs 05/07/2024 will be inadequate to maintain a secure operating state in SA .
AEMO estimates that, in the absence of sufficient market response by 1300 hrs 04/07/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Wednesday, 3 July 2024
NON-CONFORMANCE QLD1 Region Wednesday, 3 July 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: STAN-1
Duration: 03/07/2024 14:40 to 03/07/2024 14:50
Amount: -18 MW
Constraint: NC-Q_STAN-1
Auto-generated on behalf of Manager NEM Real Time Operations