112167MARKET SYSTEMS11/12/2023 06:39:14 AM

CHG0082105 | Completed | Production | BAU Retail Maintenance Release

Change Number: CHG0082105
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MDM - Meter Data Management
Change Title: BAU Retail Maintenance Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
112162GENERAL NOTICE10/12/2023 09:05:21 PM

Network Augmentation Commissioned - SA Region - 10/12/2023

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - SA Region - 10/12/2023

Commissioned: Robertstown - Bundey No. 1 275 kV Line
Bundey 275 kV Swtichyard

Manager NEM Real Time Operations
112140NON-CONFORMANCE09/12/2023 05:56:20 PM

NON-CONFORMANCE Region NSW1 Saturday, 9 December 2023

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Saturday, 9 December 2023

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BW03
Duration: 09/12/2023 17:50 to 09/12/2023 17:55
Amount: -44 MW
Constraint: NC-N_BW03

Auto-generated on behalf of Manager NEM Real Time Operations
112129RESERVE NOTICE09/12/2023 09:45:57 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 09/12/2023

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112125 is cancelled at 0945 hrs 09/12/2023.

Manager NEM Real Time Operations
112125RESERVE NOTICE09/12/2023 05:19:58 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 09/12/2023

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112119 has been updated at 0515 hrs 09/12/2023 to the following:

From 1700 hrs 09/12/2023 to 1800 hrs 09/12/2023.
The forecast capacity reserve requirement is 704 MW.
The minimum capacity reserve available is 625 MW.

AEMO is seeking a market response.

AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 1130 hrs on 09/12/2023.

Manager NEM Real Time Operations
112120GENERAL NOTICE08/12/2023 05:35:38 PM

Network Augmentation Commissioned - NSW Region - 08/12/2023

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - NSW Region - 08/12/2023

Commissioned: Wellington - Wellington North Solar Farm 7H 330 kV Line

Manager NEM Real Time Operations
112119RESERVE NOTICE08/12/2023 05:27:17 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 09/12/2023

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112081 has been updated at 1715 hrs 08/12/2023 to the following:

From 1600 hrs 09/12/2023 to 1800 hrs 09/12/2023.
The forecast capacity reserve requirement is 987 MW.
The minimum capacity reserve available is 761 MW.

AEMO is seeking a market response.

AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 1130 hrs on 09/12/2023.

Manager NEM Real Time Operations
112118NON-CONFORMANCE08/12/2023 05:10:37 PM

NON-CONFORMANCE Region QLD1 Friday, 8 December 2023

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 8 December 2023

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: SWAN_E
Duration: 08/12/2023 17:05 to 08/12/2023 17:10
Amount: 20 MW
Constraint: NC-Q_SWAN_E

Auto-generated on behalf of Manager NEM Real Time Operations
112081RESERVE NOTICE08/12/2023 01:21:12 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 09/12/2023

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1600 hrs 09/12/2023 to 1830 hrs 09/12/2023.
The forecast capacity reserve requirement is 1180 MW.
The minimum capacity reserve available is 766 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.