STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 08/05/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1700 hrs to 1800 hrs 08/05/2024.
The forecast capacity reserve requirement is 1198 MW.
The minimum capacity reserve available is 973 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
[EventId:202405020855_review] Prices for interval 02-May-2024 08:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 0850 hrs on 2 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 02-May-2024 08:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405020850_review] Prices for interval 02-May-2024 08:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 0845 hrs on 2 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 02-May-2024 08:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405020845_review] Prices for interval 02-May-2024 08:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 0840 hrs on 2 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 02-May-2024 08:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405020840_review] Prices for interval 02-May-2024 08:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 0835 hrs on 2 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 02-May-2024 08:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405020835_review] Prices for interval 02-May-2024 08:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 0830 hrs on 2 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 02-May-2024 08:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405020830_review] Prices for interval 02-May-2024 08:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 0825 hrs on 2 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 02-May-2024 08:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405011735_review] Prices for interval 01-May-2024 17:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 1 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 01-May-2024 17:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405011730_review] Prices for interval 01-May-2024 17:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1725 hrs on 1 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 01-May-2024 17:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.