Filter by category
Filter by Date
[EventId:202406141415_review] Prices for interval 14-Jun-2024 14:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1410 hrs on 14 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 14-Jun-2024 14:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202406111900_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 11 June 2024 19:00
Issued by Australian Energy Market Operator Ltd at 1900 hrs on 11 June 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 11 June 2024.
Refer to market notice: 116955
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1900 hrs on 11 June 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202406111815_review] Prices for interval 11-Jun-2024 18:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1810 hrs on 11 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Jun-2024 18:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202406111805_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 11 June 2024 18:05
Issued by Australian Energy Market Operator Ltd at 1805 hrs on 11 June 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 11 June 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1805 hrs on 11 June 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202406111810_review] Prices for interval 11-Jun-2024 18:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1805 hrs on 11 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Jun-2024 18:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202406111805_review] Prices for interval 11-Jun-2024 18:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 11 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Jun-2024 18:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202406111800_review] Prices for interval 11-Jun-2024 18:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1755 hrs on 11 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Jun-2024 18:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202406111755_review] Prices for interval 11-Jun-2024 17:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1750 hrs on 11 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Jun-2024 17:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202406111750_review] Prices for interval 11-Jun-2024 17:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1745 hrs on 11 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Jun-2024 17:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.