Market Notices

119720RESERVE NOTICE01/11/2024 05:44:45 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

[1.] From 1800 hrs 07/11/2024 to 1830 hrs 07/11/2024.
The forecast capacity reserve requirement is 535 MW.
The minimum capacity reserve available is 501 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
119719RESERVE NOTICE01/11/2024 02:43:45 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the Qld Region on 04/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the Qld region advised in AEMO Electricity Market Notice No. 119716 is cancelled at 0230 hrs 01/11/2024.

Manager NEM Real Time Operations
     
119718RESERVE NOTICE01/11/2024 02:40:17 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the Qld Region on 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the Qld region advised in AEMO Electricity Market Notice No. 119717 is cancelled at 0230 hrs 01/11/2024.

Manager NEM Real Time Operations
     
119717RESERVE NOTICE01/11/2024 12:16:02 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the Qld Region on 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the Qld region for the following period[s]:

From 1800 hrs 07/11/2024 to 1830 hrs 07/11/2024.
The forecast capacity reserve requirement is 535 MW.
The minimum capacity reserve available is 515 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
119716RESERVE NOTICE01/11/2024 12:14:08 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the Qld Region on 04/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the Qld region for the following period[s]:

[1.] From 1800 hrs 04/11/2024 to 1830 hrs 04/11/2024.
The forecast capacity reserve requirement is 535 MW.
The minimum capacity reserve available is 513 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
119715RESERVE NOTICE31/10/2024 08:46:25 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period[s]:

From 1800 hrs 07/11/2024 to 1900 hrs 07/11/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 614 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
     
119690INTER-REGIONAL TRANSFER31/10/2024 01:00:29 AM

Inter-regional transfer limit variation - Wagga B 330 kV Bus - NSW region - 31/10/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Wagga B 330 kV bus- NSW region - 31/10/2024

At 0028 hrs 31/10/2024 there was an unplanned outage of Wagga B 330 kV bus.

The following constraint set(s) invoked at 0045 hrs 31/10/2024
N-WAGGA_330_BUSB, N-JNWG_RADIAL, V-DBUSS_L and V-DBUSS_T

This constraint set(s) contains equations with the following interconnectors on the LHS.
VIC1-NSW1,N-Q-MNSP1,NSW1-QLD1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
119688INTER-REGIONAL TRANSFER30/10/2024 06:15:38 PM

Inter-regional transfer limit variation - Moorabool - Sydenham No.1 500 kV line - VIC region - 30/10/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Moorabool - Sydenham No.1 500 kV line - VIC region - 30/10/2024

A planned outage of Moorabool - Sydenham No.1 500 kV line in the VIC region was scheduled from 0500 hrs 22/10/2024 to 1930 hrs 01/11/2024.

The outage has been completed and Moorabool - Sydenham No.1 500 kV line returned to service at 1815 hrs 30/10/2024

Constraint set revoked: V-MLSY_NOEMTT_R

Manager NEM Real Time Operations
     
119626INTER-REGIONAL TRANSFER29/10/2024 11:27:47 AM

Cancellation - Inter-regional transfer limit variation - constraint automation to manage Power System Security in SA region - 29/10/2024

AEMO ELECTRICITY MARKET NOTICE

Refer AEMO Electricity Market Notice 119610

Constraint set CA_SYDS_5632AA58 was invoked from 0940 hrs until 10:45 hrs 29/10/2024.

This constraint set contains equations with the following interconnector on the LHS;
V-SA

Refer to AEMO Network Outage Scheduler (NOS) for further information.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm