Planned outage of Tailem Bend - South East 275 kV transmission line in the South Australia region beginning on 20/09/2024
The Tailem Bend - South East No 1 275 kV line in the South Australian (SA) region is planned to be out of service from 2100 hrs on 20/09/2024 to 0530 hrs on 21/09/2024.
A credible contingency event during this planned outage could cause synchronous separation of the SA region from the rest of the NEM.
During this planned outage:
- Power transfer will be restricted across the VIC - SA interconnector (Heywood interconnector); and
- Post contingent FCAS will be sourced within SA following Separation event.
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO Operations
Cancellation of a Non-Credible Contingency Event: Farrell-John Butters line and Farrell-Rosebery-Newton-Queenstown line in TAS1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: TAS1
Lines: Farrell-John Butters and Farrell-Rosebery-Newton-Queenstown
Cancellation time: 19/09/2024 12:34
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 118317
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Farrell-John Butters line and Farrell-Rosebery-Newton-Queenstown line in TAS1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: TAS1
Lines: Farrell-John Butters and Farrell-Rosebery-Newton-Queenstown
Duration: 19/09/2024 11:29 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation: Reclassification of non-credible contingency event due to existence of widespread abnormal condition - NEM region.
AEMO considers the occurrence of a non-credible contingency event due to the widespread abnormal conditions advised in AEMO Electricity Market Notice 118311 is no longer reasonably possible and accordingly its classification has reverted to non-credible.
Cancellation time: 1145 hrs 18/09/2024.
No constraints were invoked during this event
Manager NEM Real Time Operations
Reclassification of non-credible contingency event due to existence of widespread abnormal condition/s - NEM regions
AEMO has identified that a non-credible contingency event impacting the power system is more likely to occur and is considered reasonably possible because of the existence of widespread abnormal conditions namely Severe Space Weather Watch in the NEM regions.
AEMO has therefore reclassified the occurrence of a non-credible contingency event involving multiple plant due to these abnormal conditions as credible.
Duration: 0200 hrs 18/09/2024 until further notice
Need for further measures is being monitored and further measures may be implemented in line with the Power System Security Guidelines (SO_OP_3715).
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 16/09/2024
Cancellation of Actual (LOR1) condition in the NSW region - 16/09/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.118298 is cancelled at 1915 hrs 16/09/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/09/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/09/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs
The capacity reserve requirement is 1400 MW
The minimum capacity reserve available is 1274 MW
Manager NEM Real Time Operations
Cancellation of Reclassification of a Non-Credible Contingency Event - QLD region - 30/04/2019
Cancellation of Reclassification of a Non-Credible Contingency Event: Nebo SVC and the Nebo No.2 275/132kV transformer - QLD region - 30/04/2019.
Refer AEMO Electricity Market Notice 68251
Based on advice from the participant, AEMO considers the simultaneous trip of the following elements is no longer reasonably possible. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD
Equipment: Nebo SVC and the Nebo No.2 275/132kV transformer
Cancellation time: 1315 hrs 16/09/2024
Constraint set(s) revoked: Nil
Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: NSW1
Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV
Cancellation time: 12/09/2024 17:09
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 118249
Auto-generated on behalf of Manager NEM Real Time Operations