120534RECLASSIFY CONTINGENCY17/11/2024 04:35:45 AM

Reclassification of a Non-Credible Contingency Event: Palmerston - Hadspen 3 & 4 110kV line and line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Palmerston - Hadspen 3 & 4 110kV and

Duration: 17/11/2024 04:35 until further notice

Constraint set(s) invoked:
T-HAPM_110_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
     
120533RECLASSIFY CONTINGENCY17/11/2024 04:32:55 AM

Reclassification of a Non-Credible Contingency Event: Norwood - Scottsdale 1 110kV line and Norwood-Derby-Scottsdale 110kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Norwood - Scottsdale 1 110kV and Norwood-Derby-Scottsdale 110kV

Duration: 17/11/2024 04:32 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
120532RECLASSIFY CONTINGENCY17/11/2024 01:51:50 AM

Reclassification of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV

Duration: 17/11/2024 01:51 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
120521RECLASSIFY CONTINGENCY15/11/2024 08:44:02 PM

Cancellation of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Cancellation time: 15/11/2024 20:43

Constraint set(s) revoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Refer AEMO Electricity Market Notice 120519

Auto-generated on behalf of Manager NEM Real Time Operations
     
120519RECLASSIFY CONTINGENCY15/11/2024 06:43:35 PM

Reclassification of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Duration: 15/11/2024 18:43 until further notice

Constraint set(s) invoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Auto-generated on behalf of Manager NEM Real Time Operations
     
120518RECLASSIFY CONTINGENCY15/11/2024 06:39:01 PM

Cancellation of a Non-Credible Contingency Event: Collinsville - Stoney Creek 7306 132KV LINE line and Collinsville - Newlands 7121 132KV LINE line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Collinsville - Stoney Creek 7306 132KV LINE and Collinsville - Newlands 7121 132KV LINE

Cancellation time: 15/11/2024 18:38

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 120516

Auto-generated on behalf of Manager NEM Real Time Operations
     
120517RECLASSIFY CONTINGENCY15/11/2024 06:24:04 PM

Cancellation of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Cancellation time: 15/11/2024 18:23

Constraint set(s) revoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Refer AEMO Electricity Market Notice 120478

Auto-generated on behalf of Manager NEM Real Time Operations
     
120516RECLASSIFY CONTINGENCY15/11/2024 05:34:50 PM

Reclassification of a Non-Credible Contingency Event: Collinsville - Stoney Creek 7306 132KV LINE line and Collinsville - Newlands 7121 132KV LINE line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Collinsville - Stoney Creek 7306 132KV LINE and Collinsville - Newlands 7121 132KV LINE

Duration: 15/11/2024 17:34 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
120515PRICES UNCHANGED15/11/2024 05:01:32 PM

[EventId:202411151635_confirmed] Prices for interval 15-Nov-2024 16:35 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1655 hrs on 15 November 2024

PRICES ARE NOW CONFIRMED for trading interval 15-Nov-2024 16:35.

In accordance with Market Notice 120504 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm