120456PRICES UNCHANGED14/11/2024 05:31:50 PM

[EventId:202411141705_confirmed] Prices for interval 14-Nov-2024 17:05 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1730 hrs on 14 November 2024

PRICES ARE NOW CONFIRMED for trading interval 14-Nov-2024 17:05.

In accordance with Market Notice 120440 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
120454MARKET INTERVENTION15/11/2024 08:04:17 AM

Cancellation - AEMO Intervention Event - VIC region 14/11/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - VIC region 14/11/2024

Refer to Market Notice 120404

The AEMO Intervention Event and all associated directions are cancelled from 0800 hrs on 15/11/2024.


Manager NEM Real Time Operations
     
120449MARKET INTERVENTION14/11/2024 05:12:55 PM

Update Direction - Snowy Hydro Limited - MURR2-2 MURRAY2

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Snowy Hydro Limited - MURR2-2 MURRAY2

Refer AEMO Electricity Participant Notice 120435

The MURR2-2 MURRAY2 direction is now expected to stay in place until 2100 hrs 14/11/2024.

The direction update is issued at 1715 hrs 14/11/2024.

Manager NEM Real Time Operations
     
120447NON-CONFORMANCE14/11/2024 05:07:37 PM

NON-CONFORMANCE Region QLD1 Thursday, 14 November 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 14 November 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 14/11/2024 16:25 to 14/11/2024 17:05
Amount: 10 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
120446NON-CONFORMANCE14/11/2024 05:05:21 PM

NON-CONFORMANCE Region QLD1 Thursday, 14 November 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 14 November 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 14/11/2024 16:30 to 14/11/2024 17:05
Amount: -23 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
120445MARKET INTERVENTION14/11/2024 05:16:50 PM

Update Direction - Snowy Hydro Limited - MURR2-3 MURRAY2

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Snowy Hydro Limited - MURR2-3 MURRAY2

Refer AEMO Electricity Participant Notice 120436

The MURR2-3 MURRAY2 direction is now expected to stay in place until 2100 hrs 14/11/2024.

The direction update is issued at 1715 hrs 14/11/2024.

Manager NEM Real Time Operations
     
120444MARKET INTERVENTION14/11/2024 05:08:55 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 120431

The TORRB2 TORRENS ISLAN direction is now expected to start at 0700 hrs 15/11/2024.

The direction update is issued at 1705 hrs 14/11/2024.

Manager NEM Real Time Operations
     
120443MARKET INTERVENTION14/11/2024 05:14:08 PM

Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB02 JEERALANG B PO

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB02 JEERALANG B PO

Refer AEMO Electricity Participant Notice 120434

The JLB02 JEERALANG B PO direction is now expected to stay in place until 2100 hrs 14/11/2024.

The direction update is issued at 1715 hrs 14/11/2024.

Manager NEM Real Time Operations
     
120442MARKET INTERVENTION14/11/2024 05:15:29 PM

Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB01 JEERALANG B PO

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB01 JEERALANG B PO

Refer AEMO Electricity Participant Notice 120433

The JLB01 JEERALANG B PO direction is now expected to stay in place until 2100 hrs 14/11/2024.

The direction update is issued at 1715 hrs 14/11/2024.