120570RECLASSIFY CONTINGENCY17/11/2024 04:52:30 PM

Reclassification of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV

Duration: 17/11/2024 16:52 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
120569PRICES UNCHANGED17/11/2024 04:21:36 PM

[EventId:202411171555_confirmed] Prices for interval 17-Nov-2024 15:55 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1615 hrs on 17 November 2024

PRICES ARE NOW CONFIRMED for trading interval 17-Nov-2024 15:55.

In accordance with Market Notice 120558 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
120568PRICES UNCHANGED17/11/2024 04:20:17 PM

[EventId:202411171615_confirmed] Prices for interval 17-Nov-2024 16:15 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1615 hrs on 17 November 2024

PRICES ARE NOW CONFIRMED for trading interval 17-Nov-2024 16:15.

In accordance with Market Notice 120563 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
120567PRICES UNCHANGED17/11/2024 04:19:08 PM

[EventId:202411171610_confirmed] Prices for interval 17-Nov-2024 16:10 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1615 hrs on 17 November 2024

PRICES ARE NOW CONFIRMED for trading interval 17-Nov-2024 16:10.

In accordance with Market Notice 120562 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
120566PRICES UNCHANGED17/11/2024 04:17:58 PM

[EventId:202411171605_confirmed] Prices for interval 17-Nov-2024 16:05 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1615 hrs on 17 November 2024

PRICES ARE NOW CONFIRMED for trading interval 17-Nov-2024 16:05.

In accordance with Market Notice 120560 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
120565PRICES UNCHANGED17/11/2024 04:15:24 PM

[EventId:202411171600_confirmed] Prices for interval 17-Nov-2024 16:00 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1615 hrs on 17 November 2024

PRICES ARE NOW CONFIRMED for trading interval 17-Nov-2024 16:00.

In accordance with Market Notice 120559 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
120564PRICES UNCHANGED17/11/2024 04:16:48 PM

[EventId:202411171550_confirmed] Prices for interval 17-Nov-2024 15:50 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1615 hrs on 17 November 2024

PRICES ARE NOW CONFIRMED for trading interval 17-Nov-2024 15:50.

In accordance with Market Notice 120557 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
120556RESERVE NOTICE17/11/2024 03:02:36 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 18/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 120548 is cancelled at 1455 hrs 17/11/2024.

Manager NEM Real Time Operations
     
120555RECLASSIFY CONTINGENCY17/11/2024 02:52:51 PM

Reclassification of a Non-Credible Contingency Event: Bannaby - Mt Piper 5A6 500kV line and Bannaby - Mt Piper 5A7 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Bannaby - Mt Piper 5A6 500kV and Bannaby - Mt Piper 5A7 500kV

Duration: 17/11/2024 14:52 until further notice

Constraint set(s) invoked:
N-5A6+5A7_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1


Auto-generated on behalf of Manager NEM Real Time Operations
     