116976RESERVE NOTICE13/06/2024 03:44:12 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/06/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 0000 hrs to 0200 hrs 16/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1621 MW.

AEMO Operations
116975RESERVE NOTICE13/06/2024 03:43:12 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 15/06/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

1. From 0630 hrs to 1100 hrs 15/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1606 MW.

2. From 1330 hrs to 2359 hrs 15/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1523 MW.

AEMO Operations
116974RESERVE NOTICE13/06/2024 03:42:06 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 19/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 116973 is cancelled at 1400 hrs 13/06/2024.

AEMO Operations
116973RESERVE NOTICE12/06/2024 03:36:19 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 19/06/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

From 1730 hrs to 2100 hrs 19/06/2024.
The forecast capacity reserve requirement is 437 MW.
The minimum capacity reserve available is 436 MW.

AEMO Operations
116972RESERVE NOTICE12/06/2024 03:34:44 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 20/06/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 0000 hrs to 0030 hrs 20/06/2024.
The forecast capacity reserve requirement is 1830 MW.
The minimum capacity reserve available is 1651 MW.

AEMO Operations
116971RESERVE NOTICE12/06/2024 03:28:20 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116943 has been updated at 1400 hrs 12/06/2024 to the following:

1. From 0600 hrs to 0900 hrs 19/06/2024.
The forecast capacity reserve requirement is 1731 MW.
The minimum capacity reserve available is 1497 MW.

2. From 1630 hrs to 2359 hrs 19/06/2024.
The forecast capacity reserve requirement is 1830 MW.
The minimum capacity reserve available is 1561 MW.

AEMO Operations
116970RESERVE NOTICE12/06/2024 03:27:14 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 18/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116942 is cancelled at 1400 hrs 12/06/2024.

AEMO Operations
116969RESERVE NOTICE12/06/2024 03:26:08 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 17/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116926 is cancelled at 1400 hrs 12/06/2024.

AEMO Operations
116956PRICES SUBJECT TO REVIEW11/06/2024 06:10:22 PM

[EventId:202406111815_review] Prices for interval 11-Jun-2024 18:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1810 hrs on 11 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 11-Jun-2024 18:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs