117507MARKET SYSTEMS30/07/2024 01:27:09 PM

CHG0091507 | Production | As part of the Platform Services Patching Program, webMethods Inactive Production Application Servers in Brisbane will have critical s

Change Number: CHG0091507

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: MSATS - Business to Business data exchange

Change Title: As part of the Platform Services Patching Program, webMethods Inactive Production Application Servers in Brisbane will have critical security patches applied.

Change Start Date & Time: 26/08/2024 08:00:00 AEST
Change End Date & Time: 28/08/2024 18:00:00 AEST

Outage Start Date & Time:
Outage End Date & Time:

Environment: Production

Participant Impact and Requirements: This is the Inactive Production environment, there is no impact for external participants.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?d=pp_services_status for any planned/unplanned maintenance activities .
117477MARKET SYSTEMS26/07/2024 05:11:06 PM

CHG0091533 | Production | Planned Outage for the Gas Short Term Trading Market Systems Production.

Change Number: CHG0091533
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Short Term Trading Market
Change Title: Planned Outage for the Gas Short Term Trading Market Systems Production.

Change Start Date & Time: 08/08/2024 09:00:00 AEST
Change End Date & Time: 08/08/2024 22:00:00 AEST
Outage Start Date & Time: 08/08/2024 18:30:00 AEST
Outage End Date & Time: 08/08/2024 21:00:00 AEST
Environment: Production

Participant Impact and Requirements: Gas Short Term Trading Market (STTM) services including SWEX and MIS, SPI and SBS will not be available during the outage window in Production.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
117466GENERAL NOTICE30/07/2024 09:20:28 PM

Network Augmentation Commissioned - VIC Region - 30/07/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - VIC Region - 30/07/2024

Cressy Terminal Station has been cut into the existing Moorabool - Mortlake No.2 500 kV line to form the following circuits:

Cressy - Mortlake No.2 500 kV line
Cressy - Moorabool No.2 500 kV line

Manager NEM Real Time Operations
117412MARKET SYSTEMS22/07/2024 09:52:44 AM

CHG0090458 | Completed | Production | Planned Maintenance to Brisbane Internet firewall.

Change Number: CHG0090458
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Internet Access
Change Title: Planned Maintenance to Brisbane Internet firewall.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
117403MARKET SYSTEMS21/07/2024 02:12:21 PM

CHG0091275 | Completed | Production | MSATS - eMDM Maintenance AKS v1.28 upgrade

Change Number: CHG0091275
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: MSATS - eMDM Maintenance AKS v1.28 upgrade
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
117356GENERAL NOTICE18/07/2024 09:06:38 PM

Network Augmentation Commissioned - VIC Region - 18/07/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - VIC Region - 18/07/2024

At 2044 hrs 18,07/2024, Cressy Terminal Station has been cut into the existing Moorabool - Haunted Gully No.1 500 kV line to form the following circuits:

Cressy - Haunted Gully No 1 500 kV line
Cressy - Moorabool No 1 500 kV line

Manager NEM Real Time Operations
117354MARKET SYSTEMS16/07/2024 03:20:53 PM

CHG0090458 | Production | Planned Maintenance to Brisbane Internet firewall.

Change Number: CHG0090458
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal

Service/ Component: Internet Access
Change Title: Planned Maintenance to Brisbane Internet firewall.

Change Start Date & Time: 20/07/2024 14:00:22 AEST
Change End Date & Time: 20/07/2024 17:00:22 AEST
Outage Start Date & Time: 20/07/2024 14:30:26 AEST
Outage End Date & Time: 20/07/2024 14:35:26 AEST

Environment: Production
Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned outage:

IPWAN Participants - Nil

Lan-2-Lan VPN Participants (IPSEC) - Nil

B2B VPN - May experience a short 5-10 second drop of VPN tunnel connectivity to Brisbane DC.
Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO NSW datacenter termination point prior to this scheduled outage.

SSL VPN Participants: Nil

GASHUB: Nil

Other Impacts will have been communicated in advance.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .

117353MARKET SYSTEMS16/07/2024 03:15:24 PM

CHG0091273 | Completed | Pre-Production | Pre-Prod MASTS - eMDM Maintenance AKS v1.28 upgrade

Change Number: CHG0091273

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: MDM - Meter Data Management

Change Title: Pre-Prod MASTS - eMDM Maintenance AKS v1.28 upgrade

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
117345MARKET SYSTEMS15/07/2024 10:45:34 AM

CHG0090717 | Cancelled | Production | NSW Marketnet Router Replacement

Change Number: CHG0090717
Notification issued to: Market Notice

Notification Type: Cancelled
Change Type: Normal

Service/ Component: Market Network


Change Title: NSW Marketnet Router Replacement
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm