Market Notices

117487POWER SYSTEM EVENTS27/07/2024 10:52:18 AM

Correction - Non-credible contingency event - QLD region - 27/07/2024

AEMO ELECTRICITY MARKET NOTICE.

Correction to Market Notice 117486

Non-credible contingency event - QLD region - 27/07/2024

At 0951 hrs the H38 Goodna No. 2 275kV Bus and the H38 Goodna No. 1 275/132kV transformer tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
117486POWER SYSTEM EVENTS27/07/2024 10:26:53 AM

Non-credible contingency event - QLD region - 27/07/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - QLD region - 27/07/2024

At 0951 hrs the H3 Goodna No. 2 275kV Bus and the H3 Goodna No. 1 275/132kV transformer tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
117428NON-CONFORMANCE24/07/2024 08:55:12 AM

NON-CONFORMANCE Region QLD1 Wednesday, 24 July 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 24 July 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 24/07/2024 07:10 to 24/07/2024 08:55
Amount: -20 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
117427NON-CONFORMANCE23/07/2024 06:15:20 PM

NON-CONFORMANCE Region NSW1 Tuesday, 23 July 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Tuesday, 23 July 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: SHGEN
Duration: 23/07/2024 18:05 to 23/07/2024 18:15
Amount: -81 MW
Constraint: NC-N_SHGEN

Auto-generated on behalf of Manager NEM Real Time Operations
117387NON-CONFORMANCE20/07/2024 01:50:15 PM

NON-CONFORMANCE Region QLD1 Saturday, 20 July 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Saturday, 20 July 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: GANGARR1
Duration: 20/07/2024 12:20 to 20/07/2024 13:50
Amount: 60 MW
Constraint: NC-Q_GANGARR1

Auto-generated on behalf of Manager NEM Real Time Operations
117343NON-CONFORMANCE14/07/2024 04:50:19 PM

NON-CONFORMANCE Region QLD1 Sunday, 14 July 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 14 July 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 14/07/2024 16:35 to 14/07/2024 16:50
Amount: -66 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
117342NON-CONFORMANCE14/07/2024 01:45:18 AM

NON-CONFORMANCE Region VIC1 Sunday, 14 July 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Sunday, 14 July 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: YWPS1
Duration: 14/07/2024 01:40 to 14/07/2024 01:45
Amount: -35 MW
Constraint: NC-V_YWPS1

Auto-generated on behalf of Manager NEM Real Time Operations
117337NON-CONFORMANCE12/07/2024 07:55:20 AM

NON-CONFORMANCE Region QLD1 Friday, 12 July 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 12 July 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 12/07/2024 07:05 to 12/07/2024 07:55
Amount: -74 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
117321LOAD SHED08/07/2024 07:08:46 PM

Load Shedding Direction in the NSW Region

AEMO ELECTRICITY MARKET NOTICE

Load Shedding Direction in the NSW Region

AEMO has directed load shedding commencing at 1817 hrs 08/07/2024
in the NSW region

to maintain power system security.

The direction was issued under section 116 of the NEL, and was a clause 4.8.9 instruction under the NER.

Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm