Market Notices

118319GENERAL NOTICE19/09/2024 01:45:31 PM

Planned outage of Tailem Bend - South East 275 kV transmission line in the South Australia region beginning on 20/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Tailem Bend - South East No 1 275 kV line in the South Australian (SA) region is planned to be out of service from 2100 hrs on 20/09/2024 to 0530 hrs on 21/09/2024.

A credible contingency event during this planned outage could cause synchronous separation of the SA region from the rest of the NEM.

During this planned outage:
- Power transfer will be restricted across the VIC - SA interconnector (Heywood interconnector); and
- Post contingent FCAS will be sourced within SA following Separation event.

Refer AEMO Network Outage Schedule (NOS) for further details.

AEMO Operations
     
118314NON-CONFORMANCE18/09/2024 12:50:20 PM

NON-CONFORMANCE Region SA1 Wednesday, 18 September 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Wednesday, 18 September 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: TB2BG1, TB2BL1
Aggregate Dispatch Group: TB2HYB_ADG1
Duration: 18/09/2024 11:20 to 18/09/2024 12:50
Amount: 21 MW
Constraint: NC-S_TB2HYB_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
     
118310NON-CONFORMANCE17/09/2024 03:00:15 PM

NON-CONFORMANCE Region SA1 Tuesday, 17 September 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Tuesday, 17 September 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MANNSF2
Duration: 17/09/2024 14:10 to 17/09/2024 15:00
Amount: 23 MW
Constraint: NC-S_MANNSF2

Auto-generated on behalf of Manager NEM Real Time Operations
     
118299RESERVE NOTICE16/09/2024 07:16:21 PM

Cancellation of Actual (LOR1) condition in the NSW region - 16/09/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 16/09/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.118298 is cancelled at 1915 hrs 16/09/2024.

Manager NEM Real Time Operations
     
118298RESERVE NOTICE16/09/2024 06:16:31 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/09/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/09/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs

The capacity reserve requirement is 1400 MW
The minimum capacity reserve available is 1274 MW

Manager NEM Real Time Operations
     
118226GENERAL NOTICE10/09/2024 05:55:51 PM

Network Augmentation Commissioned - NSW Region - 10/09/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - NSW Region - 10/09/2024

At 1750 hrs, the following equipment at Buronga 330 kV substation has been commissioned:

1) Buronga 330 kV A bus.
2) Buronga 330 kV B bus.
3) Buronga No 1 330 kV capacitor.
4) Buronga No 2 330 kV capacitor.
5) Buronga No 7 330/220 kV transformer.

Manager NEM Real Time Operations
     
118214NON-CONFORMANCE10/09/2024 04:10:15 AM

NON-CONFORMANCE Region QLD1 Tuesday, 10 September 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Tuesday, 10 September 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 10/09/2024 03:50 to 10/09/2024 04:10
Amount: 39 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
118213NON-CONFORMANCE09/09/2024 05:40:17 PM

NON-CONFORMANCE Region QLD1 Monday, 9 September 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 9 September 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 09/09/2024 17:25 to 09/09/2024 17:40
Amount: -32 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
118205NON-CONFORMANCE09/09/2024 01:05:27 PM

NON-CONFORMANCE Region QLD1 Monday, 9 September 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 9 September 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 09/09/2024 12:35 to 09/09/2024 13:05
Amount: 29 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm