Filter by category
Filter by Date
Request for Generator Recall Information for the period 16/12/2024 and 17/12/2024 for Region NSW
Refer to AEMO Electricity Market Notice no. 121760, 121762, and 121765.
Please provide Generator Recall Information for the period from 16/12/2024 to 17/12/2024, by 1200 hrs on 13/12/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.
SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf
Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf
AEMO Operations
Request for Generator Recall Information for the period 16/12/2024 for Region VIC
Refer to AEMO Electricity Market Notice no. 121767.
Please provide Generator Recall Information for the period 16/12/2024, by 1200 hrs on 13/12/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.
SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf
Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf
AEMO Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 12/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1730 hrs 12/12/2024 to 1900 hrs 12/12/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1283 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 12/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1830 hrs 12/12/2024 to 1900 hrs 12/12/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1401 MW.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the VIC Region on 16/12/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following period:
[1.] From 1700 hrs 16/12/2024 to 1800 hrs 16/12/2024.
The forecast capacity reserve requirement is 578 MW.
The minimum capacity reserve available is 207 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/12/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
[1.] From 1500 hrs 16/12/2024 to 1530 hrs 16/12/2024.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 295 MW.
[2.] From 1600 hrs 16/12/2024 to 1700 hrs 16/12/2024.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 40 MW.
[3.] From 1830 hrs 16/12/2024 to 2000 hrs 16/12/2024.
The forecast capacity reserve requirement is 776 MW.
The minimum capacity reserve available is 0 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/12/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1500 hrs 16/12/2024 to 2000 hrs 16/12/2024.
The forecast capacity reserve requirement is 755 MW.
The minimum capacity reserve available is 0 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/12/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121711 has been updated at 1500 hrs 11/12/2024 to the following:
1. From 1530 hrs 16/12/2024 to 1600 hrs 16/12/2024.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 690 MW.
2. From 1630 hrs 16/12/2024 to 1930 hrs 16/12/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 292 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
Direction - SA region to AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Direction - SA region to AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer to Market Notice 121721
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN at 1600 hrs 11/12/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0830 hrs 12/12/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0930 hrs 12/12/2024 / further notice.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations