Filter by category
Filter by Date
[EventId:202312161230_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 16 December 2023 12:30
Issued by Australian Energy Market Operator Ltd at 1230 hrs on 16 December 2023
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 16 December 2023.
Refer to market notice: 112399
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1230 hrs on 16 December 2023.
This is an AEMO autogenerated Market Notice.
[EventId:202312161035_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 16 December 2023 10:35
Issued by Australian Energy Market Operator Ltd at 1035 hrs on 16 December 2023
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 16 December 2023.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1035 hrs on 16 December 2023.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202312161030_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 16 December 2023 10:30
Issued by Australian Energy Market Operator Ltd at 1030 hrs on 16 December 2023
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 16 December 2023.
Refer to market notice: 112397
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1030 hrs on 16 December 2023.
This is an AEMO autogenerated Market Notice.
[EventId:202312160935_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 16 December 2023 09:35
Issued by Australian Energy Market Operator Ltd at 0935 hrs on 16 December 2023
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 16 December 2023.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 0935 hrs on 16 December 2023.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202312151745_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 15 December 2023 17:45
Issued by Australian Energy Market Operator Ltd at 1745 hrs on 15 December 2023
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 December 2023.
Refer to market notice: 112393
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1745 hrs on 15 December 2023.
This is an AEMO autogenerated Market Notice.
[EventId:202312151705_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 15 December 2023 17:05
Issued by Australian Energy Market Operator Ltd at 1705 hrs on 15 December 2023
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 December 2023.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1705 hrs on 15 December 2023.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
STPASA - Update to the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/12/2023
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 112327 has been updated at 1400 hrs 15/12/2023 to the following:
From 1230 hrs to 1430 hrs 19/12/2023.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 798 MW.
From 1600 hrs to 2030 hrs 19/12/2023.
The forecast capacity reserve requirement is 1415 MW.
The minimum capacity reserve available is 1314 MW.
AEMO Operations
[EventId:202312151430_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 15 December 2023 14:30
Issued by Australian Energy Market Operator Ltd at 1430 hrs on 15 December 2023
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 December 2023.
Refer to market notice: 112378
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1430 hrs on 15 December 2023.
This is an AEMO autogenerated Market Notice.
[EventId:202312151235_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 15 December 2023 12:35
Issued by Australian Energy Market Operator Ltd at 1235 hrs on 15 December 2023
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 December 2023.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1235 hrs on 15 December 2023.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.