Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 27/12/2023
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 27/12/2023
Refer Market Notice 112823
The AEMO Intervention Event and all associated directions are cancelled from 1700 hrs 02/01/2024
Manager NEM Real Time Operations
Possible intervention to manage power system security in SA Region
Possible intervention to manage power system security in SA Region
The synchronous generating units currently expected to be synchronised in SA from 2100 hrs 03/01/2024 will be inadequate to maintain a secure operating state in SA.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
Possible intervention to manage power system security in SA Region
Possible intervention to manage power system security in SA Region
The synchronous generating units currently expected to be synchronised in SA from 2200 hrs 02/01/2024 will be inadequate to maintain a secure operating state in SA.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
Update - Direction - SA Region - 27/12/2023
Update - Direction - SA Region - 27/12/2023
Refer Market Notice 112823
The AEMO intervention event that commenced from interval ending 1505 hrs on 27/12/2023 is continuing.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
Update - Direction - SA Region - 27/12/2023
Update - Direction - SA Region - 27/12/2023
Refer Market Notice 112823
The AEMO intervention event that commenced from interval ending 1505 hrs on 27/12/2023 is continuing.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
Update - Direction - SA Region - 27/12/2023
Update - Direction - SA Region - 27/12/2023
Refer Market Notice 112823
The AEMO intervention event that commenced from interval ending 1505 hrs on 27/12/2023 is continuing.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - constraint automation to manage Power System Security in QLD region - 29/12/2023
Inter-regional transfer limit variation - constraint automation to manage Power System Security in QLD region - 29/12/2023
In order to maintain the power system in a secure operating state in the QLD region, AEMO has invoked automated constraint set CA_SYDS_549FBEF5 from 1650 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
N-Q-MNSP1
Manager NEM Real Time Operations
Update - Direction - SA Region - 27/12/2023
Update - Direction - SA Region - 27/12/2023
Refer Market Notice 112823
The AEMO intervention event that commenced from interval ending 1505 hrs on 27/12/2023 is continuing.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Para No.1 and No.2 275 kV SVC - SA region - 29/12/2023
Inter-regional transfer limit variation -Para No.1 and No.2 275 kV SVC - SA region - 29/12/2023
At 0355 hrs 29/12/2023 there was a short notice outage of Para No.1 and No.2 275 kV SVC.
The following constraint set(s) invoked at 0355 hrs 29/12/2023
S-X_PA_VC_2
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA,V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations