Market Notices

116689RESERVE NOTICE18/05/2024 06:42:10 PM

Cancellation of Actual (LOR1) condition in the NSW region - 18/05/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 18/05/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No. 116688 is cancelled at 1840 hrs 18/05/2024.

Manager NEM Real Time Operations
116688RESERVE NOTICE18/05/2024 05:58:11 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 18/05/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 18/05/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs

The capacity reserve requirement is 1430 MW
The minimum capacity reserve available is 1314 MW

Manager NEM Real Time Operations
116687INTER-REGIONAL TRANSFER18/05/2024 06:02:12 PM

Inter-regional transfer limit variation - Tamworth - Armidale No. 86 330 kV Line - NSW region - 19/05/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Tamworth - Armidale No. 86 330 kV Line - NSW region - 19/05/2024

A planned outage of Tamworth - Armidale No. 86 330 kV Line in the NSW region was scheduled from 0800 hrs 07/05/2024 to 1800 hrs 20/05/2024.

The outage has been rescheduled to be completed by 1200 hrs 19/05/2024.

Constraint set(s) invoked:
N-ARTW_86
N-DM_SVC
N-TW_SVC

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW1-QLD1
T-V-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
116686INTER-REGIONAL TRANSFER18/05/2024 06:06:00 PM

Inter-regional transfer limit variation - DAPTO - MARULAN 8 330KV Line- NSW region - 18/05/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - DAPTO - MARULAN 8 330KV Line - NSW region - 18/05/2024

A planned outage of DAPTO - MARULAN 8 330KV Line in the NSW region was scheduled from 0830 hrs 27/04/2024 to 1200 hrs 20/05/2024.

The outage has been completed at 1750 hrs 18/05/2024.

Constraint set(s) revoked: N-DTMN_8_15M, N-X_3L+8

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,
NSW1-QLD1,
V-S-MNSP1
VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
116616RESERVE NOTICE14/05/2024 06:24:48 PM

Cancellation of Actual (LOR1) condition in the Qld Region - 14/05/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the Qld region - 14/05/2024

The Actual LOR1 Condition in the Qld Region advised in AEMO Electricity Market Notice No.116615 is cancelled at 1815 hrs 14/05/2024.

Manager NEM Real Time Operations
116615RESERVE NOTICE14/05/2024 05:43:15 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD Region on 14/05/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 14/05/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1730 hrs.

The Actual LOR1 condition is forecast to exist until 1800 hrs.

The forecast capacity reserve requirement is 830 MW.
The minimum capacity reserve available is 727 MW.


Manager NEM Real Time Operations
116567RESERVE NOTICE09/05/2024 07:15:54 PM

Cancellation of Actual (LOR1) condition in the NSW region - 09/05/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 09/05/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.116566 is cancelled at 1915 hrs 09/05/2024.

Manager NEM Real Time Operations
116566RESERVE NOTICE09/05/2024 05:13:13 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/05/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/05/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs.

The capacity reserve requirement is 1450 MW
The minimum capacity reserve available is 964 MW

Manager NEM Real Time Operations
116548RESERVE NOTICE08/05/2024 07:11:28 PM

Cancellation of Actual (LOR1) condition in the NSW region - 08/05/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 08/05/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.116547 is cancelled at 1915 hrs 08/05/2024.

Manager NEM Real Time Operations
X