Market Notices

116987MARKET INTERVENTION13/06/2024 08:30:12 PM

Direction - QLD region 13/06/2024

AEMO ELECTRICITY MARKET NOTICE.

Direction - QLD region 13/06/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the QLD region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 2035 hrs on 13/06/2024.

Intervention pricing does not apply to this AEMO intervention event.

Manager NEM Real Time Operations
116985MARKET INTERVENTION13/06/2024 05:29:34 PM

Possible intervention to manage power system security in QLD Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in QLD region

The synchronous generating units currently expected to be synchronised in North QLD from 2100 hrs 13/06/2024 will be inadequate to maintain a secure operating state in North QLD.

AEMO estimates that, in the absence of sufficient market response by 2030 hrs 13/06/2024, AEMO may need to intervene by issuing a direction requiring one or more North QLD synchronous generating unit(s) to operate or remain synchronised to maintain power system security in QLD.

Manager NEM Real Time Operations



116984MARKET SYSTEMS13/06/2024 05:19:14 PM

CHG0089794 | Production | EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities .

Change Number: CHG0089794

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal

Service/ Component: Electricity Market Management System
Change Title: EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities .

Change Start Date & Time: 17/06/2024 08:00:00 AEST
Change End Date & Time: 19/06/2024 17:30:00 AEST
Outage Start Date & Time: 18/06/2024 13:25:00 AEST
Outage End Date & Time: 18/06/2024 13:30:00 AEST

Environment: Production
Participant Impact and Requirements: The maintenance activity is not expected to have any impact however delays to Dispatch cycles, bid submission, and outage to the AEMO Markets Portal are possible during the outage window on Tuesday 18th June around 13:25 to 13:30 AEST.CDR will not be available during the outage period.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
116983MARKET SYSTEMS13/06/2024 05:14:28 PM

CHG0090463 | Production | Planned Outage for the Gas Short Term Trading Market Systems Production.

Change Number: CHG0090463

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Short Term Trading Market
Change Title: Planned Outage for the Gas Short Term Trading Market Systems Production.

Change Start Date & Time: 19/06/2024 09:00:00 AEST
Change End Date & Time: 19/06/2024 22:00:00 AEST
Outage Start Date & Time: 19/06/2024 18:30:00 AEST
Outage End Date & Time: 19/06/2024 21:00:00 AEST

Environment: Production
Participant Impact and Requirements: Gas Short Term Trading Market (STTM) services including SWEX and MIS, SPI and SBS will not be available during the outage window in Production.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .

116982MARKET SYSTEMS13/06/2024 05:11:31 PM

CHG0090611 | Production | Changes to 7-day pre-dispatch (PD7DAY) reports to only publish 5 days.

Change Number: CHG0090611

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: EMMS - Dispatch

Change Title: Changes to 7-day pre-dispatch (PD7DAY) reports to only publish 5 days.
Change Start Date & Time: 17/06/2024 08:00:00 AEST
Change End Date & Time: 21/06/2024 17:30:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production

Participant Impact and Requirements: PD7DAY are reports published at least once a day and up to three times a day to assist with the administration of the gas industry's Gas Supply Guarantee and with short-term planning of gas supplies. AEMO has identified a performance issue with PD7DAY that has reduced the reliability of the delivery of the reports. As an interim measure, AEMO will reduce the outlook of PD7 DAY to 5 days which AEMO expects will reduce the frequency of missed reports.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
116981MARKET SYSTEMS13/06/2024 05:06:33 PM

CHG0090585 | Production | Dispatch Applications Upgrade

Change Number: CHG0090585

Notification issued to: Market Notice
Notification Type: Initial

Change Type: Normal
Service/ Component: EMMS - Dispatch
Change Title: Dispatch Applications Upgrade

Change Start Date & Time: 20/06/2024 09:00:00 AEST
Change End Date & Time: 21/06/2024 17:30:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production

Participant Impact and Requirements: Under this change, AEMO will upgrade the NEMDE solver used in Production for Dispatch, 5-Minute Predispatch, Predispatch and PD7 to a new version. AEMO will also upgrade other relevant applications for Dispatch ,5-Minute Predispatch ,Predispatch, PD7 as part of the Integrating Energy Storage Systems project (IESS).

No outage required.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
116980RESERVE NOTICE13/06/2024 03:48:04 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 21/06/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 0000 hrs to 0030 hrs 21/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1685MW.

AEMO Operations
116979RESERVE NOTICE13/06/2024 03:47:11 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 20/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116972 has been updated at 1400 hrs 13/06/2024 to the following:

1. From 0000 hrs to 0030 hrs 20/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1722 MW.

2. From 0600 hrs to 0900 hrs 20/06/2024.
The forecast capacity reserve requirement is 1698 MW.
The minimum capacity reserve available is 1587 MW.

3. From 1600 hrs to 2359 hrs 20/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1439MW.

AEMO Operations
116978RESERVE NOTICE13/06/2024 03:46:13 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116971 has been updated at 1400 hrs 13/06/2024 to the following:

1.From 0000 hrs to 0130 hrs 19/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1422 MW.

2. From 0600 hrs to 0900 hrs 19/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1410 MW.

3. From 1600 hrs to 2359 hrs 19/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1338 MW.

AEMO Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm