Market Notices

116958PRICES UNCHANGED11/06/2024 06:16:44 PM

[EventId:202406111755_confirmed] Prices for interval 11-Jun-2024 17:55 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1815 hrs on 11 June 2024

PRICES ARE NOW CONFIRMED for trading interval 11-Jun-2024 17:55.

In accordance with Market Notice 116951 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
116957PRICES UNCHANGED11/06/2024 06:15:25 PM

[EventId:202406111750_confirmed] Prices for interval 11-Jun-2024 17:50 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1815 hrs on 11 June 2024

PRICES ARE NOW CONFIRMED for trading interval 11-Jun-2024 17:50.

In accordance with Market Notice 116950 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
116944RESERVE NOTICE11/06/2024 03:07:42 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 12/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 116933 for the 12/06/2024 is cancelled at 1445 hrs 11/06/2024.

Manager NEM Real Time Operations
116943RESERVE NOTICE11/06/2024 03:27:32 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/06/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 0000 hrs to 0030 hrs 19/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1759 MW.

AEMO Operations
116942RESERVE NOTICE11/06/2024 03:26:28 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 18/06/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

1. From 0630 hrs to 0830 hrs 18/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1612 MW.

2. From 1600 hrs to 2359 hrs 18/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1455 MW.

AEMO Operations
116940NON-CONFORMANCE11/06/2024 02:25:21 PM

NON-CONFORMANCE Region QLD1 Tuesday, 11 June 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Tuesday, 11 June 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 11/06/2024 12:45 to 11/06/2024 14:25
Amount: -23 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
116933RESERVE NOTICE11/06/2024 01:09:29 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 12/06/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:

[1.] From 0830 hrs 12/06/2024 to 0900 hrs 12/06/2024.
The forecast capacity reserve requirement is 421 MW.
The minimum capacity reserve available is 393 MW.

[2.] From 0930 hrs 12/06/2024 to 1000 hrs 12/06/2024.
The forecast capacity reserve requirement is 419 MW.
The minimum capacity reserve available is 407 MW.

Manager NEM Real Time Operations
116932NON-CONFORMANCE11/06/2024 12:05:16 PM

NON-CONFORMANCE Region QLD1 Tuesday, 11 June 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Tuesday, 11 June 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 11/06/2024 11:15 to 11/06/2024 12:05
Amount: -21 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
116927NON-CONFORMANCE10/06/2024 11:40:17 PM

NON-CONFORMANCE Region QLD1 Monday, 10 June 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 10 June 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 10/06/2024 23:35 to 10/06/2024 23:40
Amount: 34 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm