STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 10/09/2024
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 118175 is cancelled at 2230 hrs 07/09/2024.
No LOR2 condition is currently forecast in the STPASA period.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 10/09/2024
AEMO ELECTRICITY MARKET NOTICE
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:
[1.] From 1830 hrs 10/09/2024 to 1900 hrs 10/09/2024.
The forecast capacity reserve requirement is 415 MW.
The minimum capacity reserve available is 385 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer AEMO Electricity Market Notice 118169
The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 09/09/2024.
The direction update is issued at 1600 hrs 07/09/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer AEMO Electricity Market Notice 118168
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 09/09/2024.
The direction update is issued at 1600 hrs 07/09/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer AEMO Electricity Market Notice 118156
The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 08/09/2024.
The direction update is issued at 1600 hrs 06/09/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer AEMO Electricity Market Notice 118155
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 08/09/2024.
The direction update is issued at 1600 hrs 06/09/2024.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Friday, 6 September 2024
NON-CONFORMANCE QLD1 Region Friday, 6 September 2024
AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:
Units: WDBESSG1, WDBESSL1
Aggregate Dispatch Group: WDBESS_ADG1
Duration: 06/09/2024 13:45 to 06/09/2024 14:30
Amount: 101 MW
Constraint: NC-Q_WDBESS_ADG1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Thursday, 5 September 2024
NON-CONFORMANCE NSW1 Region Thursday, 5 September 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MP1
Duration: 05/09/2024 22:30 to 05/09/2024 22:35
Amount: -103 MW
Constraint: NC-N_MP1
Auto-generated on behalf of Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer AEMO Electricity Market Notice 118126
The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 07/09/2024.
The direction update is issued at 1630 hrs 05/09/2024.
Manager NEM Real Time Operations