STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 24/09/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:
[1.] From 1430 hrs 24/09/2024 to 1600 hrs 24/09/2024.
The forecast capacity reserve requirement is 516 MW.
The minimum capacity reserve available is 462 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 22/09/2024
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 118358 is cancelled at 1500 hrs 21/09/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 22/09/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:
[1.] From 1930 hrs 22/09/2024 to 2030 hrs 22/09/2024.
The forecast capacity reserve requirement is 600 MW.
The minimum capacity reserve available is 545 MW.
Manager NEM Real Time Operations
CHG0098562 | Pre-Production | Pre-Production Electricity Market Management System (EMMS) Maintenance - Outages
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System_PreProd
Change Title: Pre-Production Electricity Market Management System (EMMS) Maintenance - Outages
Change Start Date & Time: 23/09/2024 14:00:00 AEST
Change End Date & Time: 26/09/2024 17:00:00 AEST
Outage Start Date & Time: 24/09/2024 10:00:00 AEST
Outage End Date & Time: 26/09/2024 17:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: This Maintenance activity may cause intermittent outages to below applications during the outage period .
Impacted Systems:
1.EMMS systems (Dispatch/ PASA/ Forecasting/ Settlements)
2.Identity Service will be running only for authentication purposes.
3.Web Portal including menu items (Markets, Internal & Public portal)
4.GSH
5.GBB
6.Any GAS systems that have a NEMA / WARA database connection.
7.MSATS
8.CDR
9.DERR
If any ongoing issues are identified, please contact the AEMO Support Hub 1300 236 600.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
CHG0098133 | Production | NEM Reform - RMI (Retail Market Improvements) MSATS 54.0
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Market Settlement & Transfer System
Change Title: NEM Reform - RMI (Retail Market Improvements) MSATS 54.0
Change Start Date & Time: 29/09/2024 10:00:00 AEST
Change End Date & Time: 29/09/2024 17:00:00 AEST
Outage Start Date & Time: 29/09/2024 10:00:00 AEST
Outage End Date & Time: 29/09/2024 14:00:00 AEST
Environment: Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.
Meter data processing and RM reports will not be available during the outage period.
User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.
MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage
NMI Discovery will not be available during the outage period.
CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/09/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1800 hrs 16/09/2024 to 1830 hrs 16/09/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1362 MW.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 17/09/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 118280 is cancelled at 1600 hrs 16/09/2024.
No LOR condition is currently forecast in the STPASA period.
AEMO Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region [beginning] on 16/09/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 118282 is cancelled at 1130 hrs 16/09/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/09/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1830 hrs 16/09/2024 to 1900 hrs 16/09/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1378 MW.
Manager NEM Real Time Operations