Filter by category
Filter by Date
CHG0095134 | Completed | Production | AEMO will be undertaking maintenance activities on the SMP system
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Cohesity
Change Title: AEMO will be undertaking maintenance activities on the SMP system
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
QNI Minor testing (NSW to Qld) 12th August 2024
Refer to market notice 116052
There is an opportunity for testing QNI Minor for flows from NSW to Qld up to 850 MW on Monday 12th August 2024 from 1100 to 1700hrs.
This test includes a trip and reclose of a line in northern NSW.
Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade
Ben Blake
AEMO Operations
NON-CONFORMANCE Region SA1 Sunday, 11 August 2024
NON-CONFORMANCE SA1 Region Sunday, 11 August 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: OSB-AG
Duration: 11/08/2024 15:30 to 11/08/2024 15:40
Amount: 52 MW
Constraint: NC-S_OSB-AG
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Sunday, 11 August 2024
NON-CONFORMANCE VIC1 Region Sunday, 11 August 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: LYA4
Duration: 11/08/2024 13:05 to 11/08/2024 13:35
Amount: -61 MW
Constraint: NC-V_LYA4
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Saturday, 10 August 2024
NON-CONFORMANCE QLD1 Region Saturday, 10 August 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 10/08/2024 01:05 to 10/08/2024 01:25
Amount: -47 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202408091940_confirmed] Prices for interval 09-Aug-2024 19:40 are now confirmed
Issued by Australian Energy Market Operator Ltd at 2000 hrs on 9 August 2024
PRICES ARE NOW CONFIRMED for trading interval 09-Aug-2024 19:40.
In accordance with Market Notice 117613 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202408092000_confirmed] Prices for interval 09-Aug-2024 20:00 are now confirmed
Issued by Australian Energy Market Operator Ltd at 2000 hrs on 9 August 2024
PRICES ARE NOW CONFIRMED for trading interval 09-Aug-2024 20:00.
In accordance with Market Notice 117617 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202408091955_confirmed] Prices for interval 09-Aug-2024 19:55 are now confirmed
Issued by Australian Energy Market Operator Ltd at 2000 hrs on 9 August 2024
PRICES ARE NOW CONFIRMED for trading interval 09-Aug-2024 19:55.
In accordance with Market Notice 117616 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202408091950_confirmed] Prices for interval 09-Aug-2024 19:50 are now confirmed
Issued by Australian Energy Market Operator Ltd at 2000 hrs on 9 August 2024
PRICES ARE NOW CONFIRMED for trading interval 09-Aug-2024 19:50.
In accordance with Market Notice 117615 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.