Filter by category
Filter by Date
Inter-regional transfer limit variation - Bungama - Davenport 275 kV line - SA region - 11/11/2024
Inter-regional transfer limit variation - Bungama - Davenport 275 kV line - SA region - 11/11/2024
At 1307 hrs 11/11/2024 there was an unplanned outage of the Bungama - Davenport 275 kV line.
The following constraint set invoked at 1315 hrs 11/11/2024
S-BGDV
This constraint sets contains equations with the following interconnectors on the LHS.
V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Direction - SA region to Synergen Power Pty Limited - MINTARO MINTARO GAS
Direction - SA region to Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer to Market Notice 120101
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Synergen Power Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS at 0530 hrs 11/11/2024
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0730 hrs 11/11/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 1500 hrs 11/11/2024 / further notice.
Synergen Power Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS
Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer to Market Notice 120221
Direction is cancelled from: 0530 hrs 11/11/2024
Manager NEM Real Time Operations
Direction - SA region to Synergen Power Pty Limited - MINTARO MINTARO GAS
Direction - SA region to Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer to Market Notice 120101
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Synergen Power Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS at 0030 hrs 11/11/2024
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0100 hrs 11/11/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 1500 hrs 11/11/2024 / further notice.
Synergen Power Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS
Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer to Market Notice 120216
Direction is cancelled from: 2345 hrs 10/11/2024
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 120194
The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 1500 hrs 11/11/2024.
The direction update is issued at 1600 hrs 10/11/2024.
Manager NEM Real Time Operations
Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS
Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer AEMO Electricity Participant Notice 120195
The MINTARO MINTARO GAS direction is now expected to stay in place until 1500 hrs 11/11/2024.
The direction update is issued at 1600 hrs 10/11/2024.
Manager NEM Real Time Operations
Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS
Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer to Market Notice 120193
Direction is cancelled from: 1630 hrs 09/11/2024
Manager NEM Real Time Operations
Direction - SA region to Synergen Power Pty Limited - MINTARO MINTARO GAS
Direction - SA region to Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer to Market Notice 120101
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Synergen Power Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS at 1600 hrs 09/11/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0700 hrs 10/11/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 1700 hrs 10/11/2024 / further notice.
Synergen Power Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations