Market Notices

117679NON-CONFORMANCE15/08/2024 10:10:17 AM

NON-CONFORMANCE Region SA1 Thursday, 15 August 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Wednesday, 14 August 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: TB2BG1, TB2BL1
Aggregate Dispatch Group: TB2HYB_ADG1
Duration: 14/08/2024 15:50 to 15/08/2024 10:10
Amount: -28 MW
Constraint: NC-S_TB2HYB_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
117678MARKET SYSTEMS15/08/2024 09:59:43 AM

CHG0095221 | Production | A production site transfer of the Electricity and Gas B2B Hub will be carried out to facilitate maintenance activities.

Change Number: CHG0095221

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal

Service/ Component: Gas Hub
Change Title: A production site transfer of the Electricity and Gas B2B Hub will be carried out to facilitate maintenance activities.

Change Start Date & Time: 25/08/2024 09:00:00 AEST
Change End Date & Time: 25/08/2024 17:00:00 AEST
Outage Start Date & Time: 25/08/2024 10:00:00 AEST
Outage End Date & Time: 25/08/2024 14:00:00 AEST

Environment: Production

Participant Impact and Requirements: The following impacts are expected during this maintenance:
- All access to the Electricity B2B Hub will be unavailable.
- All access to the Gas B2B Hub and all ebXML gateways (AEMOMIBB, AGNLGWY, LVI & VENCORP) will be unavailable. CATS and MDMT transactions for VIC/QLD will be delayed during the maintenance window.
- Users are not required to take any action due to this change, however will need to enact manual workarounds for the outage period.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.

Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .




117676NON-CONFORMANCE14/08/2024 03:20:18 PM

NON-CONFORMANCE Region SA1 Wednesday, 14 August 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Wednesday, 14 August 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: TB2BG1, TB2BL1
Aggregate Dispatch Group: TB2HYB_ADG1
Duration: 14/08/2024 10:30 to 14/08/2024 15:20
Amount: 26 MW
Constraint: NC-S_TB2HYB_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
117668MARKET SYSTEMS13/08/2024 04:39:46 PM

CHG0091459 | Production | MSATS CATS & URM Site Transfer BNE to NOR Data Centre

Change Number: CHG0091459
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: MSATS CATS & URM Site Transfer BNE to NOR Data Centre
Change Start Date & Time: 25/08/2024 10:00:00 AEST
Change End Date & Time: 25/08/2024 17:00:00 AEST
Outage Start Date & Time: 25/08/2024 11:15:00 AEST
Outage End Date & Time: 25/08/2024 11:45:00 AEST
Environment: Production
Participant Impact and Requirements: The change has some login outages that are below and will impact participants logging into the web portal for MSATS, OPDMS, NOS and EMMS production environments.
AEMO recommends users who need to use these AEMO services, login prior to the start of the outage and remain logged in.
NOTE: If you log out of this session, you will be unable to log back in until the completion of the outage.

A URM outage will occur between 11:15:00 - 11:45:00 AEST and have an expected outage duration of upto 20 minutes. During this time users will not be able to have new login sessions into TMM, OPDMS, NOS or EMMS WebPortal. Users who are already logged in will not be impacted.
The MSATS outage is 10:00:00 - 14:00:00 AEST.

Participants should be aware that:
o MSATS, Meter data processing, RM reports, B2B, B2M screen, NMI Discovery, CDR, CDP will not be available
o Production participant passwords will be retained.
o Users that log out and users that try to log in once the URM outage has commenced will only be able to log in after URM outage is complete. Users that are already logged in before the outage will not be impacted.
o Any password resets or new account creations completed during the URM outage window will need to be redone.
o MSATS and NOS Server FTP sessions will be disabled during outage - Wholesale MMS FTP will still be available.
o Plain English constraints will not be available during the URM outage timeframe via the EMMS web portal.
117651MARKET SYSTEMS12/08/2024 10:40:42 AM

CHG0095134 | Completed | Production | AEMO will be undertaking maintenance activities on the SMP system

Change Number: CHG0095134

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: Cohesity

Change Title: AEMO will be undertaking maintenance activities on the SMP system

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
117639NON-CONFORMANCE11/08/2024 03:41:15 PM

NON-CONFORMANCE Region SA1 Sunday, 11 August 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Sunday, 11 August 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: OSB-AG
Duration: 11/08/2024 15:30 to 11/08/2024 15:40
Amount: 52 MW
Constraint: NC-S_OSB-AG

Auto-generated on behalf of Manager NEM Real Time Operations
117631NON-CONFORMANCE11/08/2024 01:35:16 PM

NON-CONFORMANCE Region VIC1 Sunday, 11 August 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Sunday, 11 August 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: LYA4
Duration: 11/08/2024 13:05 to 11/08/2024 13:35
Amount: -61 MW
Constraint: NC-V_LYA4

Auto-generated on behalf of Manager NEM Real Time Operations
117624NON-CONFORMANCE10/08/2024 01:25:16 AM

NON-CONFORMANCE Region QLD1 Saturday, 10 August 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Saturday, 10 August 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 10/08/2024 01:05 to 10/08/2024 01:25
Amount: -47 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
117610MARKET SYSTEMS09/08/2024 04:46:48 PM

CHG0091753 | Completed | Pre-Production | Pre production Gas Supply Hub (GSH) Environment Outage

Change Number: CHG0091753
Notification issued to: Market Notice
Notification Type: Completed

Change Type: Normal
Service/Component: Gas Supply Hub
Change Title: Pre production Gas Supply Hub (GSH) Environment Outage

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm