Filter by category
Filter by Date
Cancellation of Actual (LOR1) condition in the NSW region - 16/09/2024
Cancellation of Actual (LOR1) condition in the NSW region - 16/09/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.118298 is cancelled at 1915 hrs 16/09/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/09/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/09/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs
The capacity reserve requirement is 1400 MW
The minimum capacity reserve available is 1274 MW
Manager NEM Real Time Operations
Network Augmentation Commissioned - NSW Region - 10/09/2024
Network Augmentation Commissioned - NSW Region - 10/09/2024
At 1750 hrs, the following equipment at Buronga 330 kV substation has been commissioned:
1) Buronga 330 kV A bus.
2) Buronga 330 kV B bus.
3) Buronga No 1 330 kV capacitor.
4) Buronga No 2 330 kV capacitor.
5) Buronga No 7 330/220 kV transformer.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Tuesday, 10 September 2024
NON-CONFORMANCE QLD1 Region Tuesday, 10 September 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 10/09/2024 03:50 to 10/09/2024 04:10
Amount: 39 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Monday, 9 September 2024
NON-CONFORMANCE QLD1 Region Monday, 9 September 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 09/09/2024 17:25 to 09/09/2024 17:40
Amount: -32 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Monday, 9 September 2024
NON-CONFORMANCE QLD1 Region Monday, 9 September 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 09/09/2024 12:35 to 09/09/2024 13:05
Amount: 29 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
Prices for intervals on 05/09/2024 from 13:55 to 15:10 are now confirmed
Refer AEMO Electricity Market Notice 118149 and 118150.
PRICES ARE NOW REVISED to Market Suspension Pricing Schedule for trading intervals on 05/09/2024 from 1355 hrs to 1510 hrs.
Manager Electricity Market Monitoring
NON-CONFORMANCE Region QLD1 Friday, 6 September 2024
NON-CONFORMANCE QLD1 Region Friday, 6 September 2024
AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:
Units: WDBESSG1, WDBESSL1
Aggregate Dispatch Group: WDBESS_ADG1
Duration: 06/09/2024 13:45 to 06/09/2024 14:30
Amount: 101 MW
Constraint: NC-Q_WDBESS_ADG1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Thursday, 5 September 2024
NON-CONFORMANCE NSW1 Region Thursday, 5 September 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MP1
Duration: 05/09/2024 22:30 to 05/09/2024 22:35
Amount: -103 MW
Constraint: NC-N_MP1
Auto-generated on behalf of Manager NEM Real Time Operations