Filter by category
Filter by Date
[EventId:202312271245_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 27 December 2023 12:45
Issued by Australian Energy Market Operator Ltd at 1245 hrs on 27 December 2023
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 27 December 2023.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1245 hrs on 27 December 2023.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202312241300_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 24 December 2023 13:00
Issued by Australian Energy Market Operator Ltd at 1300 hrs on 24 December 2023
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 24 December 2023.
Refer to market notice: 112657
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1300 hrs on 24 December 2023.
This is an AEMO autogenerated Market Notice.
[EventId:202312241130_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 24 December 2023 11:30
Issued by Australian Energy Market Operator Ltd at 1130 hrs on 24 December 2023
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 24 December 2023.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1130 hrs on 24 December 2023.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202312241030_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 24 December 2023 10:30
Issued by Australian Energy Market Operator Ltd at 1030 hrs on 24 December 2023
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 24 December 2023.
Refer to market notice: 112652
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1030 hrs on 24 December 2023.
This is an AEMO autogenerated Market Notice.
[EventId:202312240905_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 24 December 2023 09:05
Issued by Australian Energy Market Operator Ltd at 0905 hrs on 24 December 2023
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 24 December 2023.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 0905 hrs on 24 December 2023.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the Qld Region on 29/12/2023
The Forecast LOR1 condition in the Qld region advised in AEMO Electricity Market Notice No.112596 is cancelled at 1430 hrs 23/12/2023.
[No LOR condition is currently forecast in the STPASA period.]
Manager NEM RTO
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 29/12/2023
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1830 hrs to 1930 hrs 29/12/2023.
The forecast capacity reserve requirement is 1057 MW.
The minimum capacity reserve available is 1049 MW.
AEMO Operations
[EventId:202312221000_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 22 December 2023 10:00
Issued by Australian Energy Market Operator Ltd at 1000 hrs on 22 December 2023
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 December 2023.
Refer to market notice: 112588
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1000 hrs on 22 December 2023.
This is an AEMO autogenerated Market Notice.
[EventId:202312220900_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 22 December 2023 09:00
Issued by Australian Energy Market Operator Ltd at 0900 hrs on 22 December 2023
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 December 2023.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 0900 hrs on 22 December 2023.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.