[EventId:202409111310_confirmed] Prices for interval 11-Sep-2024 13:10 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1325 hrs on 11 September 2024
PRICES ARE NOW CONFIRMED for trading interval 11-Sep-2024 13:10.
In accordance with Market Notice 118229 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202409111300_confirmed] Prices for interval 11-Sep-2024 13:00 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1325 hrs on 11 September 2024
PRICES ARE NOW CONFIRMED for trading interval 11-Sep-2024 13:00.
In accordance with Market Notice 118227 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202409111325_review] Prices for interval 11-Sep-2024 13:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1320 hrs on 11 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Sep-2024 13:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202409111320_review] Prices for interval 11-Sep-2024 13:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1315 hrs on 11 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Sep-2024 13:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202409111315_review] Prices for interval 11-Sep-2024 13:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1310 hrs on 11 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Sep-2024 13:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202409111310_review] Prices for interval 11-Sep-2024 13:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1305 hrs on 11 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Sep-2024 13:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202409111305_review] Prices for interval 11-Sep-2024 13:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1300 hrs on 11 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Sep-2024 13:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202409111300_review] Prices for interval 11-Sep-2024 13:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1255 hrs on 11 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Sep-2024 13:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Network Augmentation Commissioned - NSW Region - 10/09/2024
Network Augmentation Commissioned - NSW Region - 10/09/2024
At 1750 hrs, the following equipment at Buronga 330 kV substation has been commissioned:
1) Buronga 330 kV A bus.
2) Buronga 330 kV B bus.
3) Buronga No 1 330 kV capacitor.
4) Buronga No 2 330 kV capacitor.
5) Buronga No 7 330/220 kV transformer.
Manager NEM Real Time Operations