117545NON-CONFORMANCE04/08/2024 06:30:18 AM

NON-CONFORMANCE Region QLD1 Sunday, 4 August 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 4 August 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: W/HOE#2
Duration: 04/08/2024 06:25 to 04/08/2024 06:30
Amount: -165 MW
Constraint: NC-Q_W/HOE#2

Auto-generated on behalf of Manager NEM Real Time Operations
117542NON-CONFORMANCE03/08/2024 04:35:17 PM

NON-CONFORMANCE Region NSW1 Saturday, 3 August 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Saturday, 3 August 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BW03
Duration: 03/08/2024 16:25 to 03/08/2024 16:35
Amount: 72 MW
Constraint: NC-N_BW03

Auto-generated on behalf of Manager NEM Real Time Operations
117539NON-CONFORMANCE02/08/2024 06:15:12 PM

NON-CONFORMANCE Region SA1 Friday, 2 August 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Friday, 2 August 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: TB2BG1, TB2BL1
Aggregate Dispatch Group: TB2HYB_ADG1
Duration: 02/08/2024 12:10 to 02/08/2024 18:15
Amount: 14 MW
Constraint: NC-S_TB2HYB_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
117534MARKET SYSTEMS02/08/2024 12:33:09 PM

CHG0091753 | Pre-Production | Pre production Gas Supply Hub (GSH) Environment Outage

Change Number: CHG0091753

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Gas Supply Hub

Change Title: Pre production Gas Supply Hub (GSH) Environment Outage

Change Start Date & Time: 08/08/2024 09:00:00 AEST

Change End Date & Time: 09/08/2024 17:00:00 AEST

Outage Start Date & Time: 08/08/2024 09:00:00 AEST

Outage End Date & Time: 09/08/2024 14:00:00 AEST

Environment: Pre-Production

Participant Impact and Requirements: "The AEMO Pre-production Gas Supply Hub (GSH) environment will be refreshed (GSH databases) and system will be unavailable during the outage window.

Access to Gas Suuply Hub (GSH) Trayport interface, GSH Day Ahead auction (DAA) and Pipeline capacity trading API and GSH web portal interfaces will be unavailable.

Upon completion of the outage users will be required to log in to pre-prod Gas Supply Hub Tray-port application using their production credentials as Trayport passwords in Pre-Production environment will be replaced with their Production passwords."

Support Information:

Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?d=pp_services_status for any planned/unplanned maintenance activities .
117533MARKET SYSTEMS02/08/2024 11:38:35 AM

CHG0093394 | Pre-Production | Planned Outage for the Gas Short Term Trading Market Systems SWEXIE Pre-Production.

Change Number: CHG0093394

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: STTM - Market Inputs - Manual

Change Title: Planned Outage for the Gas Short Term Trading Market Systems
SWEXIE Pre-Production.

Change Start Date & Time: 06/08/2024 18:30:00 AEST

Change End Date & Time: 06/08/2024 19:00:00 AEST

Outage Start Date & Time:

Outage End Date & Time:

Environment: Pre-Production

Participant Impact and Requirements: Gas Short Term Trading Market (STTM) SWEXIE services will not be available during the outage window in Pre-Production.

Support Information:

Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?d=pp_services_status for any planned/unplanned maintenance activities .
117530NON-CONFORMANCE01/08/2024 05:35:18 PM

NON-CONFORMANCE Region SA1 Thursday, 1 August 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Thursday, 1 August 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: TB2BG1, TB2BL1
Aggregate Dispatch Group: TB2HYB_ADG1
Duration: 01/08/2024 13:55 to 01/08/2024 17:35
Amount: 28 MW
Constraint: NC-S_TB2HYB_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
117528MARKET SYSTEMS01/08/2024 03:52:53 PM

CHG0091339 | Production | NSW Marketnet Router Replacement

Change Number: CHG0091339

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Market Network

Change Title: NSW Marketnet Router Replacement

Change Start Date & Time: 31/08/2024 14:00:31 AEST

Change End Date & Time: 31/08/2024 18:00:31 AEST

Outage Start Date & Time:

Outage End Date & Time:

Environment: Production

Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned outage on 31st Aug 2024:

IPWAN Participants - A brief interuption of up to 60 seconds while services are failover from NSW to QLD Datacenter.

Lan-2-Lan VPN Participants (IPSEC) - Up to 2 hour outage for participants who have established their VPN connection/s via the AEMO NSW datacenter termination point (202.44.78.10) only - All L2L connections should be established to both QLD / NSW.

Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO QLD datacenter termination point (202.44.76.10) prior to this scheduled outage.

B2B VPN - No impact is expected.

SSL VPN Participants: None expected as SSL VPN's are hosted on a different device.

GASHUB: No impact is expected as GASHUB is currently operating out of BNE Datacenter.

Other Impacts will have been communicated in advance.

Support Information:

Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?d=pp_services_status for any planned/unplanned maintenance activities .
117527MARKET SYSTEMS01/08/2024 03:51:13 PM

CHG0091340 | Production | QLD Marketnet Router Replacement

Change Number: CHG0091340

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Market Network

Change Title: QLD Marketnet Router Replacement

Change Start Date & Time: 14/09/2024 14:00:01 AEST

Change End Date & Time: 14/09/2024 18:00:01 AEST

Outage Start Date & Time:

Outage End Date & Time:

Environment: Production

Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned outage on the 14th September 2024:

IPWAN Participants - A brief interuption of up to 60 seconds while services are failover from QLD to NSW Datacenter.

Lan-2-Lan VPN Participants (IPSEC) - Up to 2 hour outage for participants who have established their VPN connection/s via the AEMO QLD datacenter termination point (202.44.76.10) only - All L2L connections should be established to both QLD / NSW.

Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO NSW datacenter termination point (202.44.78.10) prior to this scheduled outage.

B2B VPN - No impact is expected.

SSL VPN Participants: None expected as SSL VPN's are hosted on a different device.

GASHUB: No impact is expected as GASHUB will be failed over to the NSW Datacenter.

Other Impacts will have been communicated in advance.

Support Information:

Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?d=pp_services_status for any planned/unplanned maintenance activities .




117522MARKET SYSTEMS01/08/2024 02:19:54 PM

CHG0091298 | Production | Change to MarketNet SSL VPN

Change Number: CHG0091298

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Market Network

Change Title: Change to MarketNet SSL VPN

Change Start Date & Time: 19/08/2024 18:00:43 AEST

Change End Date & Time: 19/08/2024 22:00:43 AEST

Outage Start Date & Time:

Outage End Date & Time:

Environment: Production

Participant Impact and Requirements: A change to the MarketNet SSL VPN connection will take place on the 19th August 2024 between 6pm and 10PM AEST. There will be a 30 minute period during this change where no new VPN Connections will be able to be established.

Post the change window, participants running on an older version of the software may receive a message that the Anyconnect VPN client needs to be updated. This process should be automatic and once done VPN connectivity should be as normal.

Support Information:

Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?d=pp_services_status for any planned/unplanned maintenance activities .
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm