Market Notices

118434RESERVE NOTICE25/09/2024 01:24:21 AM

Cancellation of Actual (LOR1) condition in the SA region - 24/09/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the SA region - 24/09/2024

The Actual LOR1 Condition in the SA Region advised in AEMO Electricity Market Notice No.118433 is cancelled at 0120 hrs 25/09/2024.

Manager NEM Real Time Operations
118433RESERVE NOTICE24/09/2024 11:13:14 PM

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 24/09/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 24/09/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 2300 hrs.
The Actual LOR1 condition is forecast to exist until 0200 hrs

The capacity reserve requirement is 600 MW
The minimum capacity reserve available is 520 MW

Manager NEM Real Time Operations
118416MARKET SYSTEMS24/09/2024 10:24:04 AM

CHG0098666:Telstra Melbourne Indial (03 9609 XXXX-XXXX)

Change Number: CHG0098666
Notification issued to: Market Notice
Notification Type: Cancelled
Change Type: Normal
Service/ Component: Cisco IP Phone
Change Title: Telco Outage Notification - Telstra Melbourne Indial (03 9609 XXXX-XXXX)
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600




118415MARKET SYSTEMS24/09/2024 10:22:22 AM

CHG0098678:Telstra Melbourne Indial (03 9609 XXXX-XXXX)

Change Number: CHG0098678
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Cisco IP Phone
Change Title: Telco Outage Notification - Telstra Melbourne Indial (03 9609 XXXX-XXXX)
Change Start Date & Time: 08/10/2024 00:00:00 AEST
Change End Date & Time: 08/10/2024 06:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: Outage Duration:
3 x 15 Minutes during the window

Impacts:
Reduced redundancy for Inbound and Outbound Calls (automatically rerouted via Perth).
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
118413NON-CONFORMANCE24/09/2024 09:50:12 AM

NON-CONFORMANCE Region QLD1 Tuesday, 24 September 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Tuesday, 24 September 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: KSP1
Duration: 24/09/2024 09:20 to 24/09/2024 09:50
Amount: 48 MW
Constraint: NC-Q_KSP1

Auto-generated on behalf of Manager NEM Real Time Operations
118406MARKET SYSTEMS23/09/2024 03:44:02 PM

CHG0098666 | Production | Telco Outage Notification - Telstra Melbourne Indial (03 9609 XXXX-XXXX)

Change Number: CHG0098666

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Cisco IP Phone

Change Title: Telco Outage Notification - Telstra Melbourne Indial (03 9609 XXXX-XXXX)

Change Start Date & Time: 08/09/2024 00:00:00 AEST

Change End Date & Time: 08/09/2024 06:00:00 AEST

Outage Start Date & Time:

Outage End Date & Time:

Environment: Production

Participant Impact and Requirements: Outage Duration:
3 x 15 Minutes

Impacts:

Reduced redundancy for Inbound and Outbound Calls (automatically rerouted via Perth).

Support Information:

Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?d=pp_services_status for any planned/unplanned maintenance activities .




118405MARKET SYSTEMS23/09/2024 03:36:16 PM

CHG0098660 | Production | Telco Outage Notification - Telstra Melbourne Indial (03 9609 XXXX-XXXX)

Change Number: CHG0098660

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Cisco IP Phone

Change Title: Telco Outage Notification - Telstra Melbourne Indial (03 9609 XXXX-XXXX)

Change Start Date & Time: 24/09/2024 00:00:00 AEST

Change End Date & Time: 24/09/2024 06:00:00 AEST

Outage Start Date & Time:

Outage End Date & Time:

Environment: Production

Participant Impact and Requirements: Outage Duration:
1 x 3 Hours

Impacts:
Reduced redundancy for Inbound and Outbound Calls (automatically rerouted via Perth).

Support Information:

Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?d=pp_services_status for any planned/unplanned maintenance activities .

118389NON-CONFORMANCE23/09/2024 05:45:14 AM

NON-CONFORMANCE Region QLD1 Monday, 23 September 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 23 September 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: W/HOE#2
Duration: 23/09/2024 05:30 to 23/09/2024 05:45
Amount: -165 MW
Constraint: NC-Q_W/HOE#2

Auto-generated on behalf of Manager NEM Real Time Operations
118360NON-CONFORMANCE21/09/2024 07:20:17 PM

NON-CONFORMANCE Region NSW1 Saturday, 21 September 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Saturday, 21 September 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 21/09/2024 15:00 to 21/09/2024 19:20
Amount: 7 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm