Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 27/11/2024
Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 27/11/2024
The Actual LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121089 has been updated at 1645 hrs to the following:
The Actual LOR1 condition is forecast to exist until 1900 hrs.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 859 MW.
Manager NEM Real Time Operations
[EventId:202411271505_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 27 November 2024 15:05
Issued by Australian Energy Market Operator Ltd at 1505 hrs on 27 November 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 27 November 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1505 hrs on 27 November 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 27/11/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 27/11/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1430 hrs.
The Actual LOR1 condition is forecast to exist until 1630 hrs.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 710 MW.
Manager NEM Real Time Operations
[EventId:202411271420_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 27 November 2024 14:20
Issued by Australian Energy Market Operator Ltd at 1420 hrs on 27 November 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 27 November 2024.
Refer to market notice: 121081
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1420 hrs on 27 November 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202411271330_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 27 November 2024 13:30
Issued by Australian Energy Market Operator Ltd at 1330 hrs on 27 November 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 27 November 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1330 hrs on 27 November 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 27/11/2024
The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 121040 is cancelled at 1130 hrs 27/11/2024
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Wednesday, 27 November 2024
NON-CONFORMANCE QLD1 Region Wednesday, 27 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 27/11/2024 09:45 to 27/11/2024 10:25
Amount: 36 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Wednesday, 27 November 2024
NON-CONFORMANCE QLD1 Region Wednesday, 27 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 27/11/2024 09:55 to 27/11/2024 10:25
Amount: -17 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 27/11/2024
The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 121021 has been updated at 1000 hrs to the following:
[1.] From 1530 hrs 27/11/2024 to 1700 hrs 27/11/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 87 MW at 1530 hrs.
AEMO is seeking a market response.
AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 1330 hrs.
Manager NEM Real Time Operations