Market Notices

113051RESERVE NOTICE04/01/2024 03:05:46 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 09/01/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1430 hrs to 1600 hrs 09/01/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1119 MW.

AEMO Operations
113044NON-CONFORMANCE04/01/2024 04:45:12 AM

NON-CONFORMANCE Region QLD1 Thursday, 4 January 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 4 January 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BARCALDN
Duration: 04/01/2024 04:30 to 04/01/2024 04:45
Amount: 9 MW
Constraint: NC-Q_BARCALDN

Auto-generated on behalf of Manager NEM Real Time Operations
112961SETTLEMENTS RESIDUE01/01/2024 12:00:26 PM

[EventId:202401011200_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 01 January 2024 12:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1200 hrs on 1 January 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 1 January 2024.

Refer to market notice: 112960

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1200 hrs on 1 January 2024.

This is an AEMO autogenerated Market Notice.
112960SETTLEMENTS RESIDUE01/01/2024 10:40:20 AM

[EventId:202401011040_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 01 January 2024 10:40

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1040 hrs on 1 January 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 1 January 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1040 hrs on 1 January 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
112959SETTLEMENTS RESIDUE01/01/2024 10:30:28 AM

[EventId:202401011030_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 01 January 2024 10:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1030 hrs on 1 January 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 1 January 2024.

Refer to market notice: 112958

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1030 hrs on 1 January 2024.

This is an AEMO autogenerated Market Notice.
112958SETTLEMENTS RESIDUE01/01/2024 09:35:15 AM

[EventId:202401010935_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 01 January 2024 09:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0935 hrs on 1 January 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 1 January 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 0935 hrs on 1 January 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
112938SETTLEMENTS RESIDUE31/12/2023 11:00:27 AM

[EventId:202312311100_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 31 December 2023 11:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1100 hrs on 31 December 2023

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 31 December 2023.

Refer to market notice: 112935

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1100 hrs on 31 December 2023.

This is an AEMO autogenerated Market Notice.
112937NON-CONFORMANCE31/12/2023 10:45:13 AM

NON-CONFORMANCE Region VIC1 Sunday, 31 December 2023

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Sunday, 31 December 2023

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: GANNSF1
Duration: 31/12/2023 10:25 to 31/12/2023 10:45
Amount: 25 MW
Constraint: NC-V_GANNSF1

Auto-generated on behalf of Manager NEM Real Time Operations
112935SETTLEMENTS RESIDUE31/12/2023 10:05:26 AM

[EventId:202312311005_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 31 December 2023 10:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1005 hrs on 31 December 2023

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 31 December 2023.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1005 hrs on 31 December 2023.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm