PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 04/02/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 124059 has been updated at 1420 hrs 04/02/2025 to the following:
[1.] From 1530 hrs 04/02/2025 to 1630 hrs 04/02/2025.
The forecast capacity reserve requirement is 1663 MW.
The minimum capacity reserve available is 1277 MW.
[2.] From 1830 hrs 04/02/2025 to 2030 hrs 04/02/2025.
The forecast capacity reserve requirement is 1652 MW.
The minimum capacity reserve available is 974 MW.
Manager NEM Real Time Operations
[EventId:202502041335_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 04 February 2025 13:35
Issued by Australian Energy Market Operator Ltd at 1335 hrs on 4 February 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 4 February 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1335 hrs on 4 February 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
CHG0101137 | Completed | Production | Planned Maintenance to Norwest Marketnet Site to Site VPN Router
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Local Area Network
Change Title: Planned Maintenance to Norwest Marketnet Site to Site VPN Router
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
[EventId:202502041300_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 04 February 2025 13:00
Issued by Australian Energy Market Operator Ltd at 1300 hrs on 4 February 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 4 February 2025.
Refer to market notice: 124064
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 1300 hrs on 4 February 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202502041135_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 04 February 2025 11:35
Issued by Australian Energy Market Operator Ltd at 1135 hrs on 4 February 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 4 February 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1135 hrs on 4 February 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 04/02/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 124049 has been updated at 0400 hrs 04/02/2025 to the following:
[1.] From 1630 hrs 04/02/2025 to 2030 hrs 04/02/2025.
The forecast capacity reserve requirement is 1703 MW.
The minimum capacity reserve available is 1136 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 04/02/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1630 hrs 04/02/2025 to 2030 hrs 04/02/2025.
The forecast capacity reserve requirement is 1795 MW.
The minimum capacity reserve available is 1191 MW.
Manager NEM Real Time Operations
Update to system strength requirements in North Queensland
Refer to market notice 121468
AEMO and Powerlink are continuing to investigate system strength requirements in North Queensland.
The system normal equations have been revised to remove Gladstone >=1 requirement.
A revision to the constraint equations will be implemented at 1200 hrs on Tuesday 4th February 2025.
The new combinations have now published in a limits advice document on AEMO's website. For more information refer to the new limits advice: https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/congestion-information-resource/limits-advice
This advice contains all the combinations for Queensland for system normal cases. Additional information has been included in the limit advice to clarify the requirement to disconnect all inverters/turbines under certain system conditions.
The constraint equation in the Q-NIL set of the form below will be modified:
-Q_NIL_STRGTH_xxxx
-Q_NIL_STRGTH_xxxx_I
AEMO Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 03/02/2025
The Forecast LOR1 condition in the VIC region advised in AEMO Electricity Market Notice No. 124025 is cancelled at 1015 hrs 03/02/2025.
Manager NEM Real Time Operations