STPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 27/11/2024
The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 120828 has been updated at 2030 hrs on 22/11/2024 to the following:
[1.] From 1430 hrs 27/11/2024 to 1500 hrs 27/11/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 166 MW at 1430 hrs.
[2.] From 1600 hrs 27/11/2024 to 1900 hrs 27/11/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 283 MW at 1800 hrs.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
Inter-regional transfer limit variation - Directlink - NSW region - 22/11/2024
Inter-regional transfer limit variation - Directlink - NSW region - 22/11/2024
At 1911 hrs 22/11/2024 there was an unplanned outage of the No.2 leg of Directlink.
The following constraint set(s) invoked at 1920 hrs 22/11/2024
N-X_MBTE_2
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Strathmore - Clare South No.7208 132 kV line and Strathmore - Clare South tee King Creek No.7128 132 kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Strathmore - Clare South No.7208 132 kV and Strathmore - Clare South tee King Creek No.7128 132 kV
Cancellation time: 22/11/2024 17:34
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 120817
Auto-generated on behalf of Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Directlink - NSW Region
Inter-Regional Transfer limit variation - Directlink - NSW Region
There has been an unplanned outage of the No 2 Leg of Directlink .
The following constraint set was invoked at 1720 hrs 22/11/2024
N-X_MBTE_2
The constraint set contains the following interconnector on the left hand side.
N-Q-MNSP1
Refer AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 27/11/2024
AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1800 hrs 27/11/2024 to 1830 hrs 27/11/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 84 MW at 1800 hrs.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Strathmore - Clare South No.7208 132 kV line and Strathmore - Clare South tee King Creek No.7128 132 kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Strathmore - Clare South No.7208 132 kV and Strathmore - Clare South tee King Creek No.7128 132 kV
Duration: 22/11/2024 14:31 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: NSW1
Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV
Cancellation time: 22/11/2024 14:29
Constraint set(s) revoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
Refer AEMO Electricity Market Notice 120813
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: NSW1
Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV
Duration: 22/11/2024 13:26 until further notice
Constraint set(s) invoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of reclassification of a Non-Credible Contingency Event: Tumoulin - Woree No.877 275 kV line and Chalumbin - Turkinje No.7166 132 kV line line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Tumoulin - Woree No.877 275 kV line and Chalumbin - Turkinje No.7166 132 kV line
Cancellation time: 22/11/2024 00:10
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 120759
Manager NEM Real Time Operations