Filter by category
Filter by Date
[EventId:202412211310_confirmed] Prices for interval 21-Dec-2024 13:10 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1315 hrs on 21 December 2024
PRICES ARE NOW CONFIRMED for trading interval 21-Dec-2024 13:10.
In accordance with Market Notice 122357 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412211305_confirmed] Prices for interval 21-Dec-2024 13:05 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1315 hrs on 21 December 2024
PRICES ARE NOW CONFIRMED for trading interval 21-Dec-2024 13:05.
In accordance with Market Notice 122355 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412211300_confirmed] Prices for interval 21-Dec-2024 13:00 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1315 hrs on 21 December 2024
PRICES ARE NOW CONFIRMED for trading interval 21-Dec-2024 13:00.
In accordance with Market Notice 122352 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412211255_confirmed] Prices for interval 21-Dec-2024 12:55 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1315 hrs on 21 December 2024
PRICES ARE NOW CONFIRMED for trading interval 21-Dec-2024 12:55.
In accordance with Market Notice 122351 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
Reclassification of a Non-Credible Contingency Event: Guybal Munjan - Chalumbin 857 275kV line line and Guybal Munjan - Chalumbin 858 275kV line line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Guybal Munjan - Chalumbin 857 275kV line and Guybal Munjan - Chalumbin 858 275kV line
Duration: 21/12/2024 13:06 until further notice
Constraint set(s) invoked:
Q-RSCH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202412211240_confirmed] Prices for interval 21-Dec-2024 12:40 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1300 hrs on 21 December 2024
PRICES ARE NOW CONFIRMED for trading interval 21-Dec-2024 12:40.
In accordance with Market Notice 122347 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412211245_confirmed] Prices for interval 21-Dec-2024 12:45 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1300 hrs on 21 December 2024
PRICES ARE NOW CONFIRMED for trading interval 21-Dec-2024 12:45.
In accordance with Market Notice 122348 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412211235_confirmed] Prices for interval 21-Dec-2024 12:35 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1300 hrs on 21 December 2024
PRICES ARE NOW CONFIRMED for trading interval 21-Dec-2024 12:35.
In accordance with Market Notice 122345 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
Reclassification of a Non-Credible Contingency Event: Ross - Tully South - Woree No.8905 275 kV line line and Cardwell - Tully No.7389 132kV line line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Ross - Tully South - Woree No.8905 275 kV line and Cardwell - Tully No.7389 132kV line
Duration: 21/12/2024 12:41 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations