Market Notices

120738RESERVE NOTICE21/11/2024 10:30:09 AM

STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 26/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1430 hrs to 1830 hrs 26/11/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 269 MW at 1700 hrs.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
120733RESERVE NOTICE20/11/2024 10:14:40 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 26/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 120725 is cancelled at 2200 hrs 20/11/2024.

Manager NEM Real Time Operations
     
120725RESERVE NOTICE20/11/2024 05:10:46 PM

STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 26/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1530 hrs to 1900 hrs 26/11/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 12 MW at 1730 hrs.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
120714SETTLEMENTS RESIDUE20/11/2024 02:00:33 PM

[EventId:202411201400_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 20 November 2024 14:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1400 hrs on 20 November 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 20 November 2024.

Refer to market notice: 120709

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1400 hrs on 20 November 2024.

This is an AEMO autogenerated Market Notice.
     
120713RESERVE NOTICE20/11/2024 02:23:48 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 26/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 120702 is cancelled at 1300 hrs 20/11/2024.

AEMO Operations
     
120709SETTLEMENTS RESIDUE20/11/2024 12:40:25 PM

[EventId:202411201240_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 20 November 2024 12:40

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1240 hrs on 20 November 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 20 November 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1240 hrs on 20 November 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
120702RESERVE NOTICE20/11/2024 10:00:36 AM

STPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 26/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 120698 has been updated at 0900 hrs on 20/11/2024 to the following:

From 1600 hrs to 1900 hrs 26/11/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 142 MW at 1730 hrs.


AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
120701RECALL GEN CAPACITY20/11/2024 08:08:03 AM

Request for Generator Recall Information for the period from 25/11/2024 to 26/11/2024 for NSW Region

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice no. 120700, 120699 and 120698.

Please provide Generator Recall Information for the period from 25/11/2024 to 26/11/2024, by 1200 hrs on 21/11/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf

AEMO Operations
     
120698RESERVE NOTICE19/11/2024 10:30:52 PM

STPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 26/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 120671 has been updated at 2230 hrs on 19/11/2024 to the following:

[1.] From 1530 hrs 26/11/2024 to 1900 hrs 26/11/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 397 MW at 1800 hrs.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm