121100MARKET INTERVENTION27/11/2024 03:42:47 PM

RERT DISPATCHED

AEMO ELECTRICITY MARKET NOTICE.

AEMO Intervention Event, Reliability and Emergency Reserve Trader (RERT) - NSW1 Region- 27/11/2024

Refer AEMO Electricity Market Notice no. 121054
AEMO has dispatched/activated reserve contract(s) to maintain the power system in a Reliable operating state.
The reserve contract(s) was dispatched/activated at 15:45 hrs 27/11/2024 and is forecast to apply until 18:00 hrs 27/11/2024
AEMO has implemented an AEMO intervention event for the duration the reserve contract(s) is dispatched/activated/
To facilitate the RERT process, constraints commencing with the following identifiers may be evident at various times in dispatch,

#RT_NSW1


Manager NEM Real Time Operations
     
121099MARKET INTERVENTION27/11/2024 05:00:31 PM

Cancellation - AEMO Intervention Event - SA region 26/11/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 26/11/2024

Refer to Market Notice 121002

The AEMO Intervention Event and all associated directions are cancelled from 1700 hrs on 27/11/2024.


Manager NEM Real Time Operations
     
121098MARKET INTERVENTION27/11/2024 05:02:33 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 121096

Direction is cancelled from: 1700 hrs 27/11/2024

Manager NEM Real Time Operations
     
121097MARKET INTERVENTION27/11/2024 04:59:16 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 121031

Direction is cancelled from: 1700 hrs 27/11/2024

Manager NEM Real Time Operations
     
121096MARKET INTERVENTION27/11/2024 04:17:21 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 121048

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1700 hrs 27/11/2024.

The direction update is issued at 1620 hrs 27/11/2024.

Manager NEM Real Time Operations
     
121094MARKET INTERVENTION27/11/2024 04:00:11 PM

Direction - SA region 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 27/11/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1605 hrs on 27/11/2024.

Intervention pricing does not apply to this AEMO intervention event.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.


Manager NEM Real Time Operations
     
121091MARKET INTERVENTION27/11/2024 03:59:01 PM

Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 121074


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1600 hrs 27/11/2024
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0830 hrs 28/11/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1500 hrs 28/11/2024 / further notice.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
121090MARKET INTERVENTION27/11/2024 03:57:50 PM

Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 121074


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN at 1600 hrs 27/11/2024
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0830 hrs 28/11/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1430 hrs 28/11/2024 / further notice.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
121089RESERVE NOTICE27/11/2024 02:48:34 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 27/11/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1430 hrs.

The Actual LOR1 condition is forecast to exist until 1630 hrs.

The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 710 MW.

Manager NEM Real Time Operations
     