Market Notices

118360NON-CONFORMANCE21/09/2024 07:20:17 PM

NON-CONFORMANCE Region NSW1 Saturday, 21 September 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Saturday, 21 September 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 21/09/2024 15:00 to 21/09/2024 19:20
Amount: 7 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
118355NON-CONFORMANCE21/09/2024 11:35:22 AM

NON-CONFORMANCE Region QLD1 Saturday, 21 September 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Saturday, 21 September 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MOUSF1
Duration: 21/09/2024 10:55 to 21/09/2024 11:35
Amount: 81 MW
Constraint: NC-Q_MOUSF1

Auto-generated on behalf of Manager NEM Real Time Operations
118346NON-CONFORMANCE20/09/2024 06:25:11 PM

NON-CONFORMANCE Region QLD1 Friday, 20 September 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 20 September 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: WDBESSG1, WDBESSL1
Aggregate Dispatch Group: WDBESS_ADG1
Duration: 20/09/2024 18:10 to 20/09/2024 18:25
Amount: -63 MW
Constraint: NC-Q_WDBESS_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
118343NON-CONFORMANCE20/09/2024 05:40:18 PM

NON-CONFORMANCE Region QLD1 Friday, 20 September 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 20 September 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: WDBESSG1, WDBESSL1
Aggregate Dispatch Group: WDBESS_ADG1
Duration: 20/09/2024 17:15 to 20/09/2024 17:40
Amount: -63 MW
Constraint: NC-Q_WDBESS_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
118342GENERAL NOTICE20/09/2024 04:43:35 PM

Update - Lightning vulnerable lines in TAS region

AEMO ELECTRICITY MARKET NOTICE.

Update - Lightning vulnerable lines in TAS region

Refer to AEMO Electricity Market Notice 118320 ,118321, 118322

At 1340 hrs 19/09/2024 the Gordon - Chapel St No 1 220 kV line and the Gordon - Chapel St No 2 220 kV line tripped.
The cause of the trip was identified as due to Lightning.

In accordance with SO_OP_3715, AEMO now considers the Gordon - Chapel St No 1 220 kV line and the Gordon - Chapel St No 2 220 kV line to be vulnerable with a category of Vulnerability due to Lightning.

Manager NEM Real Time Operations
118331MARKET SYSTEMS20/09/2024 10:19:05 AM

CHG0098562 | Pre-Production | Pre-Production Electricity Market Management System (EMMS) Maintenance - Outages

Change Number: CHG0098562

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Electricity Market Management System_PreProd

Change Title: Pre-Production Electricity Market Management System (EMMS) Maintenance - Outages

Change Start Date & Time: 23/09/2024 14:00:00 AEST
Change End Date & Time: 26/09/2024 17:00:00 AEST
Outage Start Date & Time: 24/09/2024 10:00:00 AEST
Outage End Date & Time: 26/09/2024 17:00:00 AEST

Environment: Pre-Production

Participant Impact and Requirements: This Maintenance activity may cause intermittent outages to below applications during the outage period .

Impacted Systems:
1.EMMS systems (Dispatch/ PASA/ Forecasting/ Settlements)
2.Identity Service will be running only for authentication purposes.
3.Web Portal including menu items (Markets, Internal & Public portal)
4.GSH
5.GBB
6.Any GAS systems that have a NEMA / WARA database connection.
7.MSATS
8.CDR
9.DERR

If any ongoing issues are identified, please contact the AEMO Support Hub 1300 236 600.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
118319GENERAL NOTICE19/09/2024 01:45:31 PM

Planned outage of Tailem Bend - South East 275 kV transmission line in the South Australia region beginning on 20/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Tailem Bend - South East No 1 275 kV line in the South Australian (SA) region is planned to be out of service from 2100 hrs on 20/09/2024 to 0530 hrs on 21/09/2024.

A credible contingency event during this planned outage could cause synchronous separation of the SA region from the rest of the NEM.

During this planned outage:
- Power transfer will be restricted across the VIC - SA interconnector (Heywood interconnector); and
- Post contingent FCAS will be sourced within SA following Separation event.

Refer AEMO Network Outage Schedule (NOS) for further details.

AEMO Operations
118314NON-CONFORMANCE18/09/2024 12:50:20 PM

NON-CONFORMANCE Region SA1 Wednesday, 18 September 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Wednesday, 18 September 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: TB2BG1, TB2BL1
Aggregate Dispatch Group: TB2HYB_ADG1
Duration: 18/09/2024 11:20 to 18/09/2024 12:50
Amount: 21 MW
Constraint: NC-S_TB2HYB_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
118313MARKET SYSTEMS18/09/2024 12:09:04 PM

CHG0098133 | Production | NEM Reform - RMI (Retail Market Improvements) MSATS 54.0

Change Number: CHG0098133
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Market Settlement & Transfer System
Change Title: NEM Reform - RMI (Retail Market Improvements) MSATS 54.0
Change Start Date & Time: 29/09/2024 10:00:00 AEST
Change End Date & Time: 29/09/2024 17:00:00 AEST
Outage Start Date & Time: 29/09/2024 10:00:00 AEST
Outage End Date & Time: 29/09/2024 14:00:00 AEST
Environment: Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.

Meter data processing and RM reports will not be available during the outage period.

User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.

MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage

NMI Discovery will not be available during the outage period.

CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm