119667GENERAL NOTICE29/10/2024 09:02:13 PM

Update - Pre dispatch demand forecast - Qld region

AEMO ELECTRICITY MARKET NOTICE

Update - Pre dispatch demand forecast - Qld region

Refer market notice: 119666

The issue relating to the Queensland Pre dispatch demand forecast has been resolved.

Manager NEM Real Time Operations
     
119666GENERAL NOTICE29/10/2024 07:43:09 PM

Pre dispatch demand forecast - Qld region

AEMO ELECTRICITY MARKET NOTICE

Pre dispatch demand forecast - Qld region

AEMO is aware of an error in the Queensland pre dispatch demand forecast.
AEMO is currently working to resolve the issue.
Dispatch results are not impacted.


Manager NEM Real Time Operations
     
119644MINIMUM SYSTEM LOAD29/10/2024 03:03:58 PM

Forecast Minimum System Load 1 (MSL1) in the VIC Region on 02/11/2024

AEMO ELECTRICITY MARKET NOTICE

Update to Market Notice 119571 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region on 02/11/2024.

Minimum regional demand is forecast to be 1457 MW at 1230 hrs, and the advisory threshold is:
MSL1 - 1695 MW
MSL2 - 1195 MW
MSL3 - 695 MW


The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1130 hrs to 1400 hrs 02/11/2024.

AEMO Operations
     
119584RESERVE NOTICE28/10/2024 03:46:18 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 29/10/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 119566 is cancelled at 1530 hrs 28/10/2024

Manager NEM Real Time Operations
     
119578MINIMUM SYSTEM LOAD28/10/2024 03:33:55 PM

Cancellation of Minimum System Load 1 (MSL1) in the VIC Region on 03/11/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - MSL1- VIC Region at 1400 hrs 28/10/2024.

Refer to Market Notice 119497 for Forecast MSL1.


AEMO Operations
     
119571MINIMUM SYSTEM LOAD28/10/2024 03:04:41 PM

Forecast Minimum System Load 1 (MSL1) in the VIC Region on 02/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region on 02/11/2024.

Minimum regional demand is forecast to be 1491 MW at 1230 hrs, and the advisory threshold is:
MSL1 = 1695 MW
MSL2 = 1195 MW
MSL3 = 695 MW

The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1100 hrs to 1330 hrs 02/11/2024.

AEMO Operations
     
119566RESERVE NOTICE28/10/2024 01:03:59 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 29/10/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:

[1.] From 1800 hrs 29/10/2024 to 1900 hrs 29/10/2024.
The forecast capacity reserve requirement is 683 MW.
The minimum capacity reserve available is 589 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
119461RESERVE NOTICE27/10/2024 12:48:22 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 29/10/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 119460 is cancelled at 0030 hrs 27/10/2024.

No LOR2 condition is currently forecast in the STPASA period.

Manager NEM Real Time Operations
     
119460RESERVE NOTICE27/10/2024 12:22:21 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 29/10/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

From 1800 hrs to 1830 hrs 29/10/2024.
The forecast capacity reserve requirement is 836 MW.
The minimum capacity reserve available is 824 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     