Market Notices

119321RESERVE NOTICE24/10/2024 02:50:57 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 30/10/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following periods:

From 1830 hrs to 1900 hrs 30/10/2024.
The forecast capacity reserve requirement is 1130 MW.
The minimum capacity reserve available is 1120 MW.

AEMO Operations
     
119319RESERVE NOTICE24/10/2024 02:53:53 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 29/10/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following periods:

From 1800 hrs to 1900 hrs 29/10/2024.
The forecast capacity reserve requirement is 1040 MW.
The minimum capacity reserve available is 995 MW.

AEMO Operations
     
119318RESERVE NOTICE24/10/2024 02:55:06 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region 28/10/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following periods:

[1.] From 1730 hrs to 1800 hrs 28/10/2024.
The forecast capacity reserve requirement is 1044 MW.
The minimum capacity reserve available is 768 MW.

[2.] From 1900 hrs to 2030 hrs 28/10/2024.
The forecast capacity reserve requirement is 1052 MW.
The minimum capacity reserve available is 673 MW.

AEMO Operations
     
119311RESERVE NOTICE24/10/2024 02:41:53 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 24/10/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 119211 has been updated at 1400 hrs to the following:

[1.] From 1800 hrs 24/10/2024 to 2030 hrs 24/10/2024.
The forecast capacity reserve requirement is 1420 MW.
The minimum capacity reserve available is 1209 MW.

Manager NEM Real Time Operations
     
119263RESERVE NOTICE23/10/2024 08:23:49 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 24/10/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 119213 has been updated at 2000 hrs to the following:

[1.] From 1730 hrs 24/10/2024 to 1900 hrs 24/10/2024.
The forecast capacity reserve requirement is 1172 MW.
The minimum capacity reserve available is 910 MW.

Manager NEM Real Time Operations
     
119229RESERVE NOTICE23/10/2024 03:05:00 PM

STPASA - Cancellation of the Forecast Lack of Reserve Level 1 (LOR1) in the NSW Region on 25/10/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 119162 is cancelled at 1400 hrs 23/10/2024.

AEMO Operations
     
119213RESERVE NOTICE23/10/2024 01:02:06 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 24/10/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:

[1.] From 1730 hrs 24/10/2024 to 1930 hrs 24/10/2024.
The forecast capacity reserve requirement is 1187 MW.
The minimum capacity reserve available is 774 MW.

Manager NEM Real Time Operations
     
119211RESERVE NOTICE23/10/2024 01:03:39 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 24/10/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1800 hrs 24/10/2024 to 1930 hrs 24/10/2024.
The forecast capacity reserve requirement is 1420 MW.
The minimum capacity reserve available is 1306 MW.

Manager NEM Real Time Operations
     
119208NON-CONFORMANCE23/10/2024 12:25:15 PM

NON-CONFORMANCE Region SA1 Wednesday, 23 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Wednesday, 23 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: DALNTH1
Duration: 23/10/2024 12:15 to 23/10/2024 12:25
Amount: 14 MW
Constraint: NC-S_DALNTH1

Auto-generated on behalf of Manager NEM Real Time Operations
     