Market Notices

112200RECALL GEN CAPACITY12/12/2023 11:01:01 AM

Request for Generator Recall Information for 14/12/2023 for NSW Region

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice no. 112198.

Please provide Generator Recall Information for the period 14/12/2023, by 1200 hrs on 13/12/2023 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf

AEMO Operations
112188INTER-REGIONAL TRANSFER11/12/2023 04:31:45 PM

Inter-regional transfer limit variation - Blyth West- Munno Para 275 kV Line - SA region - 11/12/2023

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Blyth West- Munno Para 275 kV Line - SA region - 11/12/2023

At 1446 hrs 11/12/2023 there was an unplanned outage of Blyth West- Munno Para 275 kV Line.

However, due to the concurrent Non-credible contingency event - SA region - 11/12/2023, refer AEMO Electricity Market Notice 112187, additional inter-regional constraints were not required until the remaining Mintaro - Waterloo 132 kV Line was returned to service.

The following constraint set(s) invoked at 1610 hrs 11/12/2023
S-BWMP

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
112050INTER-REGIONAL TRANSFER08/12/2023 01:18:51 AM

Cancellation Inter-Regional Transfer limit variation - Murraylink control unavailable (SA Region)

AEMO ELECTRICITY MARKET NOTICE

Cancellation Inter-Regional Transfer limit variation - Murraylink control unavailable (SA Region)

Refer AEMO Electricity Market Notice 112048

AEMO has been notified that the controls to vary Murraylink output are now available.

Constraint set I-CTRL_ISSUE_ML revoked at 0115 hrs.

Manager NEM Real Time Operations
112049INTER-REGIONAL TRANSFER08/12/2023 01:17:46 AM

Cancellation Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)

AEMO ELECTRICITY MARKET NOTICE

Cancellation Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region).

Refer AEMO Electricity Market Notice 112047

AEMO has been notified that the controls to vary Directlink output are now available.

Constraint set I-CTRL_ISSUE_TE revoked at 0115 hrs.

Manager NEM Real Time Operations
112048INTER-REGIONAL TRANSFER08/12/2023 12:22:34 AM

Inter-Regional Transfer limit variation - Murraylink control unavailable (SA Region)

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Murraylink control unavailable (SA Region)

AEMO has been notified that the controls to vary Murraylink output are unavailable until further notice.

Constraint set I-CTRL_ISSUE_ML invoked from 0025 hrs.

The constraint set contains equations with the following interconnector on the LHS:

V-S-MNSP1


Manager NEM Real Time Operations
112047INTER-REGIONAL TRANSFER08/12/2023 12:23:43 AM

Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)

AEMO has been notified that the controls to vary Directlink output are unavailable until further notice.

Constraint set I-CTRL_ISSUE_TE invoked from 0025 hrs.

The constraint set contains equations with the following interconnector on the LHS:

N-Q-MNSP1


Manager NEM Real Time Operations
112003INTER-REGIONAL TRANSFER04/12/2023 04:44:47 PM

Inter-Regional Transfer limit variation - Murraylink power transfer limit reduction due to high temperature.

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Murraylink power transfer limit reduction due to high temperature.

Murraylink power transfer limit has been reduced based on APA advice, consistent with the high ambient temperatures in the vicinity of Murraylink (Berri and Redcliffe).

Constraint sets I-SVML_165 and I-VSML_165 invoked from 1640 hrs.

The constraint set contains equations with the following interconnector on the LHS:

V-S-MNSP1

Refer to AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
111971INTER-REGIONAL TRANSFER03/12/2023 04:38:17 PM

Inter-regional transfer limit variation - H2 South Pine 275kV SVC - QLD region - 03/12/2023

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - H2 South Pine 275kV SVC - QLD region - 03/12/2023

At 1626 hrs 03/12/2023 there was an unplanned outage of H2 South Pine 275kV SVC.

The following constraint set(s) invoked at 1630 hrs 03/12/2023
Q-SP_VC

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW1 - QLD1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm