Filter by category
Filter by Date
[EventId:202410111830_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 11 October 2024 18:30
Issued by Australian Energy Market Operator Ltd at 1830 hrs on 11 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 11 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.
The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1830 hrs on 11 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202410111600_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 11 October 2024 16:00
Issued by Australian Energy Market Operator Ltd at 1600 hrs on 11 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 11 October 2024.
Refer to market notice: 118776
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1600 hrs on 11 October 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202410111435_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 11 October 2024 14:35
Issued by Australian Energy Market Operator Ltd at 1435 hrs on 11 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 11 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1435 hrs on 11 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202410110530_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 11 October 2024 05:30
Issued by Australian Energy Market Operator Ltd at 0530 hrs on 11 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 11 October 2024.
Refer to market notice: 118764
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.
The negative residue constraint NRM_QLD1_NSW1 ceased operating at 0530 hrs on 11 October 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202410101900_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 10 October 2024 19:00
Issued by Australian Energy Market Operator Ltd at 1900 hrs on 10 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 10 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.
The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1900 hrs on 10 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202410100600_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 10 October 2024 06:00
Issued by Australian Energy Market Operator Ltd at 0600 hrs on 10 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 10 October 2024.
Refer to market notice: 118739
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.
The negative residue constraint NRM_QLD1_NSW1 ceased operating at 0600 hrs on 10 October 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202410100200_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 10 October 2024 02:00
Issued by Australian Energy Market Operator Ltd at 0200 hrs on 10 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 10 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.
The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 0200 hrs on 10 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202410092000_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 09 October 2024 20:00
Issued by Australian Energy Market Operator Ltd at 2000 hrs on 9 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 9 October 2024.
Refer to market notice: 118735
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.
The negative residue constraint NRM_QLD1_NSW1 ceased operating at 2000 hrs on 9 October 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202410091835_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 09 October 2024 18:35
Issued by Australian Energy Market Operator Ltd at 1835 hrs on 9 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 9 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.
The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1835 hrs on 9 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.