Cancellation of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: NSW1
Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV
Cancellation time: 08/12/2023 19:09
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 112116
Auto-generated on behalf of Manager NEM Real Time Operations
Network Augmentation Commissioned - NSW Region - 08/12/2023
Network Augmentation Commissioned - NSW Region - 08/12/2023
Commissioned: Wellington - Wellington North Solar Farm 7H 330 kV Line
Manager NEM Real Time Operations
Cancellation of the reclassification of a Non-Credible Contingency Event: Para-Templers West and Magill-Torrens Island A 275kV lines in SA due to severe weather warning.
Cancellation of the reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.
AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any severe weather warning in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: SA
Lines: Para-Templers West and Magill-Torrens Island A 275kV lines
Cancellation time: 08/12/2023 17:00
Constraint set(s) revoked: Nil
Refer AEMO Electricity Market Notice 112082
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: NSW1
Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV
Duration: 08/12/2023 17:05 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Tungatinah-Lake Echo-Waddamana 1 110kV line and Tungatinah-Waddamana 2 110kV line in TAS1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: TAS1
Lines: Tungatinah-Lake Echo-Waddamana 1 110kV and Tungatinah-Waddamana 2 110kV
Cancellation time: 08/12/2023 14:44
Constraint set(s) revoked:
T-TUWA12_110_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE
Refer AEMO Electricity Market Notice 112079
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of the Reclassification of a Non-Credible Contingency Event: Loss of Sheffield 220 kV switchyard (all 220 kV buses) in Tas due to planned work
Cancellation of the reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to planned work. AEMO considers the simultaneous trip of the following plant is no longer reasonably possible. Accordingly its classification has reverted to a non-credible contingency event.
Region: TAS1
Plant: Sheffield 220 kV switchyard (all 220 kV buses)
Cancellation time: 08/12/2023 14:05 hrs
Constraint set revoked:
T-SH_220_N-2
Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1
Refer AEMO Electricity Market Notice 112059
Manager NEM Real Time Operations
Cancellation: Reclassification of non-credible contingency event due to existence of widespread abnormal conditions - SA region.
AEMO considers the occurrence of a non-credible contingency event due to the widespread abnormal conditions advised in AEMO Electricity Market Notice 112074 is no longer reasonably possible and accordingly its classification has reverted to non-credible.
Cancellation time: 1400 hrs 08/10/2023.
Constraint set revoked:
I-VS_250
Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Farrell-John Butters line and Farrell-Rosebery-Newton-Queenstown line in TAS1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: TAS1
Lines: Farrell-John Butters and Farrell-Rosebery-Newton-Queenstown
Cancellation time: 08/12/2023 13:54
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 112078
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of the Reclassification of a Non-Credible Contingency Event: South East - Tailem Bend No.1 and No.2 275 kV lines in SA due to severe weather warning.
Cancellation of the reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.
AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. Accordingly its classification has reverted to a non-credible contingency event.
Region: SA
Lines: South East - Tailem Bend No.1 and No.2 275 kV lines
Cancellation time: 08/12/2023 14:00 hrs
Constraint set revoked: S-SETB_N-2
Constraint set contains the following interconnector(s) on the left hand side: V-SA, NSW1-QLD1
Refer AEMO Electricity Market Notice 112056
Manager NEM Real Time Operations