[EventId:202312081445_review] Prices for interval 08-Dec-2023 14:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1440 hrs on 8 December 2023
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Dec-2023 14:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 09/12/2023
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Periods:
[1.] From 1530 hrs 09/12/2023 to 1600 hrs 09/12/2023.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1253 MW.
[2.] From 1830 hrs 09/12/2023 to 1900 hrs 09/12/2023.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1239 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 08/12/2023
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
From 1630 hrs 08/12/2023 to 1730 hrs 08/12/2023.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1070 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 09/12/2023
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1600 hrs 09/12/2023 to 1830 hrs 09/12/2023.
The forecast capacity reserve requirement is 1180 MW.
The minimum capacity reserve available is 766 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Update to the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 09/12/2023
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112041 has been updated at 1100 hrs 08/12/2023 to the following:
From 1530 hrs 09/12/2023 to 1830 hrs 09/12/2023.
The forecast capacity reserve requirement is 1250 MW.
The minimum capacity reserve available is 776 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
[EventId:202312081035_review] Prices for interval 08-Dec-2023 10:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1030 hrs on 8 December 2023
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Dec-2023 10:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202312081030_review] Prices for interval 08-Dec-2023 10:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1025 hrs on 8 December 2023
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Dec-2023 10:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202312081025_review] Prices for interval 08-Dec-2023 10:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1020 hrs on 8 December 2023
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Dec-2023 10:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202312081020_review] Prices for interval 08-Dec-2023 10:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1015 hrs on 8 December 2023
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Dec-2023 10:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.