118752MARKET INTERVENTION10/10/2024 03:32:39 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Market Notice 118751

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 0430 hrs 11/10/2024.

The direction update is issued at 1530 hrs 10/10/2024.

Manager NEM Real Time Operations
118751MARKET INTERVENTION10/10/2024 03:01:09 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Market Notice 118717

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 12/10/2024.

The direction update is issued at 1500 hrs 10/10/2024.

Manager NEM Real Time Operations
118750MARKET INTERVENTION10/10/2024 02:59:37 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer AEMO Electricity Market Notice 118716

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0430 hrs 11/10/2024.

The direction update is issued at 1500 hrs 10/10/2024.

Manager NEM Real Time Operations
118746MARKET INTERVENTION10/10/2024 02:58:34 PM

Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 118715


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1500 hrs 10/10/2024
Type of resource: generating unit
Required actions: remain synchronised and follow dispatch targets at 1400 hrs 11/10/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 12/10/2024 / further notice.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
118740SETTLEMENTS RESIDUE10/10/2024 06:00:29 AM

[EventId:202410100600_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 10 October 2024 06:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0600 hrs on 10 October 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 10 October 2024.

Refer to market notice: 118739

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.

The negative residue constraint NRM_QLD1_NSW1 ceased operating at 0600 hrs on 10 October 2024.

This is an AEMO autogenerated Market Notice.
118739SETTLEMENTS RESIDUE10/10/2024 02:00:20 AM

[EventId:202410100200_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 10 October 2024 02:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0200 hrs on 10 October 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 10 October 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.

The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 0200 hrs on 10 October 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
118737SETTLEMENTS RESIDUE09/10/2024 08:00:28 PM

[EventId:202410092000_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 09 October 2024 20:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2000 hrs on 9 October 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 9 October 2024.

Refer to market notice: 118735

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.

The negative residue constraint NRM_QLD1_NSW1 ceased operating at 2000 hrs on 9 October 2024.

This is an AEMO autogenerated Market Notice.
118735SETTLEMENTS RESIDUE09/10/2024 06:35:31 PM

[EventId:202410091835_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 09 October 2024 18:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1835 hrs on 9 October 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 9 October 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.

The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1835 hrs on 9 October 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
118734SETTLEMENTS RESIDUE09/10/2024 06:30:29 PM

[EventId:202410091830_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 09 October 2024 18:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1830 hrs on 9 October 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 9 October 2024.

Refer to market notice: 118726

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.

The negative residue constraint NRM_QLD1_NSW1 ceased operating at 1830 hrs on 9 October 2024.

This is an AEMO autogenerated Market Notice.