Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer AEMO Electricity Market Notice 118751
The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 0430 hrs 11/10/2024.
The direction update is issued at 1530 hrs 10/10/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer AEMO Electricity Market Notice 118717
The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 12/10/2024.
The direction update is issued at 1500 hrs 10/10/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer AEMO Electricity Market Notice 118716
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0430 hrs 11/10/2024.
The direction update is issued at 1500 hrs 10/10/2024.
Manager NEM Real Time Operations
Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 118715
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1500 hrs 10/10/2024
Type of resource: generating unit
Required actions: remain synchronised and follow dispatch targets at 1400 hrs 11/10/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 12/10/2024 / further notice.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
[EventId:202410100600_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 10 October 2024 06:00
Issued by Australian Energy Market Operator Ltd at 0600 hrs on 10 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 10 October 2024.
Refer to market notice: 118739
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.
The negative residue constraint NRM_QLD1_NSW1 ceased operating at 0600 hrs on 10 October 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202410100200_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 10 October 2024 02:00
Issued by Australian Energy Market Operator Ltd at 0200 hrs on 10 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 10 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.
The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 0200 hrs on 10 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202410092000_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 09 October 2024 20:00
Issued by Australian Energy Market Operator Ltd at 2000 hrs on 9 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 9 October 2024.
Refer to market notice: 118735
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.
The negative residue constraint NRM_QLD1_NSW1 ceased operating at 2000 hrs on 9 October 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202410091835_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 09 October 2024 18:35
Issued by Australian Energy Market Operator Ltd at 1835 hrs on 9 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 9 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.
The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1835 hrs on 9 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202410091830_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 09 October 2024 18:30
Issued by Australian Energy Market Operator Ltd at 1830 hrs on 9 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 9 October 2024.
Refer to market notice: 118726
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.
The negative residue constraint NRM_QLD1_NSW1 ceased operating at 1830 hrs on 9 October 2024.
This is an AEMO autogenerated Market Notice.