116052GENERAL NOTICE09/04/2024 11:26:28 AM

Increase to QNI limit to next hold point of 850 MW NSW to Qld

AEMO ELECTRICITY MARKET NOTICE

Refer to market notices 114742.

AEMO, TransGrid, Powerlink have reviewed the test results following the QNI minor testing on 15th February 2024. The next hold point can now be released.

The hold point of 850 MW from NSW to Qld will be implemented as of 1000 hrs 10th April 2024.

Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade

Ben Blake
AEMO Operations
116047NON-CONFORMANCE08/04/2024 03:05:14 PM

NON-CONFORMANCE Region QLD1 Monday, 8 April 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 8 April 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 08/04/2024 15:00 to 08/04/2024 15:05
Amount: -43 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
115974GENERAL NOTICE09/04/2024 06:18:24 PM

Update - Network Augmentation Commissioned - QLD Region - 09/04/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Network Augmentation Commissioned - QLD Region - 09/04/2024

Refer Market notice: 115957

Guybal Munjan 275 kV Switching Station has been cut into the existing Ross - Chalumbin No.858 275 kV line to form the following circuits:

H93 Guybal Munjan - H32 Chalumbin No.858 275 kV line
H13 Ross - H93 Guybal Munjan No.8916 275 kV line

Manager NEM Real Time Operations
115969NON-CONFORMANCE05/04/2024 09:05:15 AM

NON-CONFORMANCE Region QLD1 Friday, 5 April 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 5 April 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 05/04/2024 08:45 to 05/04/2024 09:05
Amount: -49 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
115957GENERAL NOTICE04/04/2024 02:36:06 PM

Network Augmentation Commissioned - QLD Region - 04/04/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - QLD Region - 04/04/2024

Commissioned:

H93 Guybal Munjan 275 kV Switching Station
H13 Ross - H93 Guybal Munjan No.8916 275 kV line

Manager NEM Real Time Operations
115950NON-CONFORMANCE04/04/2024 03:10:16 AM

NON-CONFORMANCE Region QLD1 Thursday, 4 April 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 4 April 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: KAREEYA1
Duration: 04/04/2024 03:00 to 04/04/2024 03:10
Amount: -17 MW
Constraint: NC-Q_KAREEYA1

Auto-generated on behalf of Manager NEM Real Time Operations
115915NON-CONFORMANCE02/04/2024 01:15:11 AM

NON-CONFORMANCE Region NSW1 Tuesday, 2 April 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Tuesday, 2 April 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP6
Duration: 02/04/2024 01:10 to 02/04/2024 01:15
Amount: 34 MW
Constraint: NC-N_VP6

Auto-generated on behalf of Manager NEM Real Time Operations
115906NON-CONFORMANCE01/04/2024 07:35:18 AM

NON-CONFORMANCE Region NSW1 Monday, 1 April 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Monday, 1 April 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MP1
Duration: 01/04/2024 07:30 to 01/04/2024 07:35
Amount: 19 MW
Constraint: NC-N_MP1

Auto-generated on behalf of Manager NEM Real Time Operations
115874NON-CONFORMANCE29/03/2024 08:00:14 AM

NON-CONFORMANCE Region VIC1 Friday, 29 March 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Friday, 29 March 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: YWPS3
Duration: 29/03/2024 07:55 to 29/03/2024 08:00
Amount: -16 MW
Constraint: NC-V_YWPS3

Auto-generated on behalf of Manager NEM Real Time Operations