Filter by category
Filter by Date
Request for Generator Recall Information for 14/12/2023 for NSW Region
Refer to AEMO Electricity Market Notice no. 112198.
Please provide Generator Recall Information for the period 14/12/2023, by 1200 hrs on 13/12/2023 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.
SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf
Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf
AEMO Operations
NON-CONFORMANCE Region SA1 Tuesday, 12 December 2023
NON-CONFORMANCE SA1 Region Tuesday, 12 December 2023
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: NBHWF1
Duration: 12/12/2023 09:00 to 12/12/2023 09:25
Amount: 17 MW
Constraint: NC-S_NBHWF1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Monday, 11 December 2023
NON-CONFORMANCE QLD1 Region Monday, 11 December 2023
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GSTONE5
Duration: 11/12/2023 10:30 to 11/12/2023 10:35
Amount: 15 MW
Constraint: NC-Q_GSTONE5
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Saturday, 9 December 2023
NON-CONFORMANCE NSW1 Region Saturday, 9 December 2023
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BW03
Duration: 09/12/2023 17:50 to 09/12/2023 17:55
Amount: -44 MW
Constraint: NC-N_BW03
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Friday, 8 December 2023
NON-CONFORMANCE QLD1 Region Friday, 8 December 2023
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: SWAN_E
Duration: 08/12/2023 17:05 to 08/12/2023 17:10
Amount: 20 MW
Constraint: NC-Q_SWAN_E
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Friday, 8 December 2023
NON-CONFORMANCE NSW1 Region Friday, 8 December 2023
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: SUNTPSF1
Duration: 08/12/2023 12:35 to 08/12/2023 12:50
Amount: 76 MW
Constraint: NC-N_SUNTPSF1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Wednesday, 6 December 2023
NON-CONFORMANCE NSW1 Region Wednesday, 6 December 2023
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: SUNTPSF1
Duration: 06/12/2023 07:30 to 06/12/2023 08:45
Amount: 51 MW
Constraint: NC-N_SUNTPSF1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Tuesday, 5 December 2023
NON-CONFORMANCE NSW1 Region Tuesday, 5 December 2023
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: NEWENSF1
Duration: 05/12/2023 12:25 to 05/12/2023 12:45
Amount: 25 MW
Constraint: NC-N_NEWENSF1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Monday, 4 December 2023
NON-CONFORMANCE QLD1 Region Monday, 4 December 2023
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: STAN-1
Duration: 04/12/2023 09:20 to 04/12/2023 09:25
Amount: -31 MW
Constraint: NC-Q_STAN-1
Auto-generated on behalf of Manager NEM Real Time Operations