112201RECALL GEN CAPACITY12/12/2023 10:59:40 AM

Request for Generator Recall Information for 14/12/2023 for QLD Region

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice no. 112198. Additional generation in QLD could assist in alleviating the forecast LOR condition in NSW.

Please provide Generator Recall Information for the period 14/12/2023, by 1200 hrs on 13/12/2023 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf

AEMO Operations
112200RECALL GEN CAPACITY12/12/2023 11:01:01 AM

Request for Generator Recall Information for 14/12/2023 for NSW Region

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice no. 112198.

Please provide Generator Recall Information for the period 14/12/2023, by 1200 hrs on 13/12/2023 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf

AEMO Operations
112199NON-CONFORMANCE12/12/2023 09:25:17 AM

NON-CONFORMANCE Region SA1 Tuesday, 12 December 2023

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Tuesday, 12 December 2023

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: NBHWF1
Duration: 12/12/2023 09:00 to 12/12/2023 09:25
Amount: 17 MW
Constraint: NC-S_NBHWF1

Auto-generated on behalf of Manager NEM Real Time Operations
112173NON-CONFORMANCE11/12/2023 10:35:17 AM

NON-CONFORMANCE Region QLD1 Monday, 11 December 2023

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 11 December 2023

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: GSTONE5
Duration: 11/12/2023 10:30 to 11/12/2023 10:35
Amount: 15 MW
Constraint: NC-Q_GSTONE5

Auto-generated on behalf of Manager NEM Real Time Operations
112140NON-CONFORMANCE09/12/2023 05:56:20 PM

NON-CONFORMANCE Region NSW1 Saturday, 9 December 2023

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Saturday, 9 December 2023

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BW03
Duration: 09/12/2023 17:50 to 09/12/2023 17:55
Amount: -44 MW
Constraint: NC-N_BW03

Auto-generated on behalf of Manager NEM Real Time Operations
112118NON-CONFORMANCE08/12/2023 05:10:37 PM

NON-CONFORMANCE Region QLD1 Friday, 8 December 2023

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 8 December 2023

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: SWAN_E
Duration: 08/12/2023 17:05 to 08/12/2023 17:10
Amount: 20 MW
Constraint: NC-Q_SWAN_E

Auto-generated on behalf of Manager NEM Real Time Operations
112080NON-CONFORMANCE08/12/2023 12:50:18 PM

NON-CONFORMANCE Region NSW1 Friday, 8 December 2023

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Friday, 8 December 2023

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: SUNTPSF1
Duration: 08/12/2023 12:35 to 08/12/2023 12:50
Amount: 76 MW
Constraint: NC-N_SUNTPSF1

Auto-generated on behalf of Manager NEM Real Time Operations
112022NON-CONFORMANCE06/12/2023 08:45:17 AM

NON-CONFORMANCE Region NSW1 Wednesday, 6 December 2023

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Wednesday, 6 December 2023

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: SUNTPSF1
Duration: 06/12/2023 07:30 to 06/12/2023 08:45
Amount: 51 MW
Constraint: NC-N_SUNTPSF1

Auto-generated on behalf of Manager NEM Real Time Operations
112009NON-CONFORMANCE05/12/2023 12:45:20 PM

NON-CONFORMANCE Region NSW1 Tuesday, 5 December 2023

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Tuesday, 5 December 2023

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: NEWENSF1
Duration: 05/12/2023 12:25 to 05/12/2023 12:45
Amount: 25 MW
Constraint: NC-N_NEWENSF1

Auto-generated on behalf of Manager NEM Real Time Operations