Non-credible contingency event - SA region - 11/12/2023
Non-credible contingency event - SA region - 11/12/2023
At 0444 hrs the Mintaro - Waterloo 132 kV Line tripped and the Clare North - Mintaro 132 kV Line tripped at the Mintaro end only.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Cancellation Inter-Regional Transfer limit variation - Murraylink control unavailable (SA Region)
Cancellation Inter-Regional Transfer limit variation - Murraylink control unavailable (SA Region)
Refer AEMO Electricity Market Notice 112048
AEMO has been notified that the controls to vary Murraylink output are now available.
Constraint set I-CTRL_ISSUE_ML revoked at 0115 hrs.
Manager NEM Real Time Operations
Cancellation Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)
Cancellation Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region).
Refer AEMO Electricity Market Notice 112047
AEMO has been notified that the controls to vary Directlink output are now available.
Constraint set I-CTRL_ISSUE_TE revoked at 0115 hrs.
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Murraylink control unavailable (SA Region)
Inter-Regional Transfer limit variation - Murraylink control unavailable (SA Region)
AEMO has been notified that the controls to vary Murraylink output are unavailable until further notice.
Constraint set I-CTRL_ISSUE_ML invoked from 0025 hrs.
The constraint set contains equations with the following interconnector on the LHS:
V-S-MNSP1
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)
Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)
AEMO has been notified that the controls to vary Directlink output are unavailable until further notice.
Constraint set I-CTRL_ISSUE_TE invoked from 0025 hrs.
The constraint set contains equations with the following interconnector on the LHS:
N-Q-MNSP1
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Murraylink power transfer limit reduction due to high temperature.
Inter-Regional Transfer limit variation - Murraylink power transfer limit reduction due to high temperature.
Murraylink power transfer limit has been reduced based on APA advice, consistent with the high ambient temperatures in the vicinity of Murraylink (Berri and Redcliffe).
Constraint sets I-SVML_165 and I-VSML_165 invoked from 1640 hrs.
The constraint set contains equations with the following interconnector on the LHS:
V-S-MNSP1
Refer to AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - H2 South Pine 275kV SVC - QLD region - 03/12/2023
Inter-regional transfer limit variation - H2 South Pine 275kV SVC - QLD region - 03/12/2023
At 1626 hrs 03/12/2023 there was an unplanned outage of H2 South Pine 275kV SVC.
The following constraint set(s) invoked at 1630 hrs 03/12/2023
Q-SP_VC
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW1 - QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations