Inter-regional transfer limit variation - Tamworth - Armidale No. 86 330 kV Line - NSW region - 19/05/2024
Inter-regional transfer limit variation - Tamworth - Armidale No. 86 330 kV Line - NSW region - 19/05/2024
A planned outage of Tamworth - Armidale No. 86 330 kV Line in the NSW region was scheduled from 0800 hrs 07/05/2024 to 1800 hrs 20/05/2024.
The outage has been rescheduled to be completed by 1200 hrs 19/05/2024.
Constraint set(s) invoked:
N-ARTW_86
N-DM_SVC
N-TW_SVC
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW1-QLD1
T-V-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - DAPTO - MARULAN 8 330KV Line- NSW region - 18/05/2024
Inter-regional transfer limit variation - DAPTO - MARULAN 8 330KV Line - NSW region - 18/05/2024
A planned outage of DAPTO - MARULAN 8 330KV Line in the NSW region was scheduled from 0830 hrs 27/04/2024 to 1200 hrs 20/05/2024.
The outage has been completed at 1750 hrs 18/05/2024.
Constraint set(s) revoked: N-DTMN_8_15M, N-X_3L+8
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,
NSW1-QLD1,
V-S-MNSP1
VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Saturday, 18 May 2024
NON-CONFORMANCE QLD1 Region Saturday, 18 May 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 18/05/2024 02:40 to 18/05/2024 02:45
Amount: -14 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Thursday, 16 May 2024
NON-CONFORMANCE VIC1 Region Thursday, 16 May 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: NPS
Duration: 16/05/2024 15:20 to 16/05/2024 15:25
Amount: -15 MW
Constraint: NC-V_NPS
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Friday, 10 May 2024
NON-CONFORMANCE QLD1 Region Friday, 10 May 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: OAKEY2SF
Duration: 10/05/2024 08:35 to 10/05/2024 10:05
Amount: 35 MW
Constraint: NC-Q_OAKEY2SF
Auto-generated on behalf of Manager NEM Real Time Operations
Inter-regional transfer limit variation - Blyth West to Munno Para 275 kV line - SA region - 08/05/2024
Inter-regional transfer limit variation - Blyth West to Munno Para 275 kV line - SA region - 08/05/2024
At 1536 hrs 08/05/2024 there was an unplanned outage of Blyth West to Munno Para 275 kV line.
The following constraint set(s) invoked at 1545 hrs 08/05/2024
S-X_BGBW+BWMP
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Tamworth No. 1 330 kV Bus - NSW region - 08/05/2024
Inter-regional transfer limit variation - Tamworth No. 1 330 kV Bus - NSW region - 08/05/2024
A planned outage of Tamworth No. 1 330 kV Bus in the NSW region was scheduled from 1200 hrs 08/05/2024 to 1800 hrs 10/05/2024.
The outage has been cancelled at 1154 hrs 08/05/2024
Constraint set(s) revoked: N-TW_330_BUS1, N-LDTW_84
This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1
N-Q-MNSP1
T-V-MNSP1
Manager NEM Real Time Operations
Inter-regional transfer limit variation - DAPTO - MARULAN 8 330KV LINE - NSW region - 07/05/2024
Inter-regional transfer limit variation - DAPTO - MARULAN 8 330KV LINE - NSW region - 07/05/2024
A planned outage of DAPTO - MARULAN 8 330KV LINE in the NSW region was scheduled from 0830 hrs 27/04/2024 to 1000 hrs 07/05/2024.
The outage has been rescheduled to be completed by 1200 hrs 08/05/2024.
Constraint set(s) invoked: N-DTMN_8_15M
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Friday, 3 May 2024
NON-CONFORMANCE VIC1 Region Friday, 3 May 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: YWPS3
Duration: 03/05/2024 07:00 to 03/05/2024 07:10
Amount: -45 MW
Constraint: NC-V_YWPS3
Auto-generated on behalf of Manager NEM Real Time Operations