Market Notices

114686INTER-REGIONAL TRANSFER14/02/2024 01:24:53 AM

Inter-regional transfer limit variation: Moorabool - Sydenham No1 and No2 500 kV lines - VIC region - 13/02/2024 -

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation: Moorabool - Sydenham No1 and No2 500 kV lines - 13/02/2024

At 1308 hrs 13/02/2024 the Moorabool - Sydenham No1 and No2 500 kV lines tripped.

Refer Market notices 114577 and 114625.

The following constraint set(s) are invoked :

V-X_MLSY
F-V-X_ML_BUSTIE_500
I-VS_050

These constraint set contains equations with the following interconnectors on the LHS.

T-V-MNSP1
V-SA
V-S-MNSP1
VIC1- NSW1

Refer to the Network outage scheduler (NOS) for more details:

Manager NEM Real Time Operations
114436INTER-REGIONAL TRANSFER08/02/2024 10:24:54 AM

Inter-regional transfer limit variation - Dapto - Marulan 8 Line - NSW region - 08/02/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Dapto - Marulan 8 Line - NSW region - 08/02/2024

At 1015 hrs 08/02/2024 there was a short notice outage of Dapto - Marulan 8 Line


The following constraint set(s) invoked at 1015 hrs 08/02/2024
N-DTMN_8_15M

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
114429INTER-REGIONAL TRANSFER07/02/2024 07:06:39 PM

Inter-regional transfer limit variation - South Pine SVC - QLD region - 07/02/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - South Pine SVC - QLD region - 07/02/2024

At 1850 hrs 07/02/2024 there was an unplanned outage of the South Pine SVC.

The following constraint set(s) invoked at 1855 hrs 07/02/2024
Q-SP_VC

This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,N-Q-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
114407INTER-REGIONAL TRANSFER06/02/2024 09:12:48 PM

Inter-regional transfer limit variation - Greenbank 275kV SVC - QLD region - 06/02/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Greenbank 275kV SVC - QLD region - 06/02/2024

At 2102 hrs 06/02/2024 there was an unplanned outage of the Greenbank 275kV SVC

The following constraint set(s) invoked at 2110 hrs 06/02/2024
Q-GB_VC

This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,N-Q-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
114401RESERVE NOTICE06/02/2024 07:43:29 PM

Cancellation of Actual (LOR1) condition in the QLD region - 06/02/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the QLD region - 06/02/2024

The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.114399 is cancelled at 1945 hrs 06/02/2024.

Manager NEM Real Time Operations
114399RESERVE NOTICE06/02/2024 07:22:16 PM

Update - Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 06/02/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 06/02/2024

The actual LOR1 condition in the Qld region advised in AEMO Electricity Market Notice No. 114397 has been updated at 1915 hrs 06/02/2024 to the following:

The Actual LOR1 condition is forecast to exist until 2000 hrs.

The forecast capacity reserve requirement is 1045 MW.
The minimum capacity reserve available is 950 MW.

Manager NEM Real Time Operations
114397RESERVE NOTICE06/02/2024 06:08:41 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 06/02/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 06/02/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs

The capacity reserve requirement is 1095 MW
The minimum capacity reserve available is 892 MW

Manager NEM Real Time Operations
113998RESERVE NOTICE29/01/2024 08:23:46 PM

Cancellation of Actual (LOR1) condition in the QLD region - 29/01/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the QLD region - 29/01/2024

The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.113994 is cancelled at 2000 hrs 29/01/2024.

Manager NEM Real Time Operations
113994RESERVE NOTICE29/01/2024 06:12:37 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 29/01/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 29/01/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1810 hrs.

The Actual LOR1 condition is forecast to exist until 1900 hrs.

The forecast capacity reserve requirement is 1197 MW.
The minimum capacity reserve available is 1026 MW.

Manager NEM Real Time Operations